◉ RECORDS OF ALL INSPECTIONS AND MX SHALL BE MAINTAINED
ON PREMISES FOR A MIN. OF __________ YEARS. Answer: 3
◉ THE BUILDING OWNER SHALL ASSIGN A(N) ____________ TO
COMPLY WITH REQUIREMENTS. Answer: IMPAIRMENT
COORDINATOR
◉ REGULAR MX AND MINOR REPAIRS NOT AFFECTING MORE
THAN ________ FLOOR(S) ARE CONSIDERED PLANNED REMOVAL
FROM SERVICE. Answer: 1
◉ SHUTDOWNS AFFECTING MORE THAN _________ FLOOR(S) ARE
CONSIDERED UNPLANNED OUT OF SERVICE CONDITIONS. Answer:
1
◉ NOTIFICATION TO FDNY IS NOT REQUIRED, PROVIDED SYSTEM
IS RETURNED TO SERVICE WITHIN ______ HOURS. Answer: 8
,◉ FOR UNPLANNED REMOVAL FROM SERVICE, THE COF HOLDER
SHALL IMMEDIATELY REPORT CONDITION TO THE ___________ AND
THE FIRE DEPT. Answer: OWNER OF THE BUILDING
◉ IF A MINOR DEFECT IS OBSERVED, IT SHALL BE CORRECTED
WITHIN _________ DAYS OR IT WILL BE CONSIDERED AN
IMPAIRMENT. Answer: 30
◉ WHAT DOES "OOS" STAND FOR? Answer: OUT OF SERVICE
◉ OOS SYSTEMS SHALL BE IDENTIFIED BY PLACING ________ AT
FIRE DEPT. CONNECTIONS, SYS. CONTROL VALVES, AND FIRE
COMMAND CENTER Answer: TAGS
◉ A _______ SHALL BE REQUIRED TO POST TAGS AT MAIN CONTROL
VALVE AND ANY SECTIONAL VALVES. Answer: MASTER FIRE
SUPPRESSION PIPING CONTRACTOR
◉ __________ SHALL BE POSTED ON THE TAG INDICATING BOTH
STATIC AND FLOW PRESSURES BEFORE AND AFTER. Answer:
DRAIN TEST RESULTS
◉ GREEN TAGS INDICATE THAT __________. Answer: NO
IMPAIRMENT WAS FOUND
,◉ GREEN TAGS WILL BE PLACED ON THE ____________. Answer: MAIN
CONTROL VALVE
◉ SYSTEMS PARTIALLY OR FULLY OUT OF SERVICE SHALL HAVE A
____________ TAG PLACED ON THE MAIN CONTROL VALVE. Answer:
RED
◉ A _________ DISC OF 8-9 INCHES SHALL BE PLACED ON
CONNECTIONS TO INDICATE THE SYSTEM IS FULLY OUT OF
SERVICE. Answer: WHITE
◉ A ________ DISC OF 8-9 INCHES SHALL BE PLACED ON
CONNECTIONS TO INDICATE THE SYSTEM IS PARTIALLY OUT OF
SERVICE. Answer: BLUE
◉ THE IMPAIRMENT COORDINATOR WILL NOTIFY THE ___________
CARRIER, CENTRAL STATION AND OCCUPANTS. Answer:
INSURANCE
◉ PRIOR TO RETURNING A SYS. TO SERVICE, THE ___________ SHALL
ENSURE THAT NECESSARY TESTS AND INSPECTIONS ARE
CONDUCTED. Answer: IMPAIRMENT COORDINATOR
, ◉ GLYCERIN NOT GREATER THAN _________ PERCENT OR GLYCOL
NOT GREATHER THAN ________ PERCENT SHALL BE USED TO
PROTECT FROM FREEZING. Answer: 50, 40
◉ THE COF NUMBER AND SIGNATURE OF COF HOLDER SHALL BE
POSTED NEAR THE ____________. Answer: MAIN CONTROL VALVE
◉ __________ SHALL BE READILY AVAILABLE TO ANY
REPRESENTATIVE OF THE FIRE DEPT. THESE ARE TO BE
MAINTAINED ON SITE FOR 3 YEARS. Answer: RECORDS
◉ FAILURE TO MAKE INSPECTIONS MAY RESULT IN __________ OF
THE COF AND COURT PROCEEDINGS. Answer: REVOCATION
◉ THE COF HOLDER MAY INSPECT, TEST, AND PERFORM ROUTINE
MX IF THEY HOLD THE FOLLOWING CERTS: Answer:
REFRIGERATION OPERATING ENGINEER, HIGH PRESSURE
OPERATING ENGINEER, AND NYS HIGH PRESSURE OPERATING
ENGINEER.
◉ A ________ CAN INSPECT, MAINTAIN, TEST, AND REPAIR ALL FIRE
STANDPIPE AND SPRINKLER SYSTEMS. Answer: MASTER FIRE
SUPPRESSION PIPING CONTRACTOR (MFSPC)