Practice Questions
realigning funds between activities that are below the level of control for that appropriation
category does not require a reprogramming action, and that this type of funds transfer can be
approved by - correct answer ✔✔ the Program Manager.
most reprogramming actions are approved at the Service or agency level using - correct answer
✔✔ below threshold reprogramming
four reasons that requires prior approval from Congress for reprogramming authority - correct
answer ✔✔ Moving funds between appropriations
Increasing quantities of major systems
New starts
Designated special interest items
Congress recognizes the need for some flexibility in budget execution, and provides DOD with a
method ________ to make limited changes in its appropriated funding. - correct answer ✔✔
reprogramming
major legal provisions that concern funds execution - correct answer ✔✔ Anti-deficiency Act,
Misappropriation Act, Bona Fide Need Rule
Anti-deficiency Act - correct answer ✔✔ obligation in excess of the appropriated amount
obligation in excess of the appropriated amount
Misappropriation Act - correct answer ✔✔ Not used for the programs and purpose for which
the appropriation is made
,Bona Fide Need Rule - correct answer ✔✔ Goods and Services used only during current fiscal
year
How to pay for remaining outlay requirements after funds have been canceled? - correct answer
✔✔ Must be paid for using current year funds
Cancelled Funds - correct answer ✔✔ After 5 years "expired" period has passed
Expired Funds - correct answer ✔✔ May be used for expenditures or adjustments on existing
obligations.
How long do funds remain in expired account? - correct answer ✔✔ 5 years
Budget Authority - correct answer ✔✔ Spending Limit
Commitment - correct answer ✔✔ Administrative reservation of funds
Obligation - correct answer ✔✔ Legal Reservation of Funds
Expenditure - correct answer ✔✔ issuance of a Government check. (write a check)
Outlay - correct answer ✔✔ clears the treasury department (bank pays check from account)
Continuing Resolution - correct answer ✔✔ Provides "stopgap" funding to keep affected
agencies operating for a specified period of time (spelled out in the resolution), Normally does
not specify dollar amounts of budget authority, Permits activities to operate at "the current rate
of operations",
, Role of House & Senate Budget Committees - correct answer ✔✔ budget resolution
Role of House & Senate Armed Services Committees - correct answer ✔✔ authorization
Role of House & Senate Appropriations Committees - correct answer ✔✔ appropriation
three basic activities that must be completed after the President's Budget is submitted to
Congress - correct answer ✔✔ Budget Resolution, Authorization Bill, Appropriation Bill
Program Objective Memorandum (POM) - correct answer ✔✔ documents service fiscal
requirements-prioritize programs/budget, budget year +next 4 years
BES Budget Estimate Submission - correct answer ✔✔ same as POM but only concentrates on
the budget year
four phases of the PPBE process and docs produced - correct answer ✔✔ Planning-DPG defense
planning guidance
four phases of the PPBE process and docs produced - correct answer ✔✔ Planning,
Programming, Budgeting, Execution
four phases of the PPBE process and docs produced - correct answer ✔✔ Budgeting-BES budget
estimate submission
four phases of the PPBE process and docs produced - correct answer ✔✔ Execution- RMD
resource management decision/president's budget