Solutions
"Quality is meeting the acceptance criteria 100% of the time."
Correct Answers True
"Standardize" is one of the 5 S's. Correct Answers True
3D CAD is the same as BIM. Correct Answers False
A BIM design begins with intelligent objects such as walls, roof,
and windows Correct Answers True
A BIM file contains construction details, performance
characteristics, and product specs. Correct Answers True
A BIM model is a 3D representation of the physical and
functional characteristics of a building. Correct Answers True
A BIM model serves as a shared knowledge resource for the
entire design and build team. Correct Answers True
A change order adjustment amount does not include general
overhead and profit. Correct Answers False
A claim can only be made after the project is complete. Correct
Answers False
A clear expression of employee concern should be a policy
component of a safety manual. Correct Answers True
,A company's managerial commitment should include safety.
Correct Answers True
A comprehensive quality control plan is the best way to control
quality during construction. Correct Answers True
A construction team does not need diversity. Correct Answers
False
A good win-win example is using recycled concrete as a base
material for new roadways or driveways. Correct Answers True
A job hazard analysis focuses on jobs and tasks. Correct
Answers True
A LEAN program generates value. Correct Answers True
A LEAN program, once initiated, is good for many years
without improvement. Correct Answers False
A network diagram is nothing more than a work plan. Correct
Answers True
A poor quality design is not a contractor risk. Correct Answers
False
A preparatory inspection is unnecessary to avoid miscues and
rework. Correct Answers False
A project control system utilizes the plans, specs, estimate, and
schedule. Correct Answers True
, A project debriefing is not meant to be a training mechanism.
Correct Answers False
A project is considered totally complete even if paperwork has
not been delivered to the owner. Correct Answers False
A project may go forward without paperwork. Correct Answers
False
A public project has less governmental involvement than a
private project. Correct Answers False
A risk mitigation plan happens before construction starts and
does not vary thereafter. Correct Answers False
A short-interval schedule is not the same as a look-ahead
schedule. Correct Answers False
A stop sign is an example of an administrative control. Correct
Answers True
A tailgate meeting to review safety procedures is risk
management. Correct Answers True
A team should measure its performance against its goals.
Correct Answers True
A time extension is a contract adjustment used when a monetary
adjustment is not owed. Correct Answers False