• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 103 pages
Exam (elaborations)

Cisa Domain 3 2026|Verified Questions And 100% Correct Solutions|Updated Version !!!|A+ Graded|Exam Ready|95% Success Rate

Document preview thumbnail
Preview 4 out of 103 pages

CISA DOMAIN 3 2026|VERIFIED QUESTIONS AND 100% CORRECT SOLUTIONS|UPDATED VERSION !!!|A+ GRADED|EXAM READY|95% SUCCESS RATE This document provides verified questions and 100% correct solutions for the CISA Domain 3 exam in 2026. It is an updated version, A+ graded, exam-ready, and boasts a 95% success rate. It's designed to help you thoroughly prepare and excel in your CISA Domain 3 exam.

Content preview

100% CORRECT SOLUTIONS|UPDATED VERSION
!!!|A+ GRADED|EXAM READY|95% SUCCESS

A3-1 Who should review and approve system deliverables as they are defined and
accomplished, to ensure the successful completion and implementation of a new business
system application?



A. User management

B. Project steering committee

C. Senior management

D. Quality assurance staff - ANSWER A is the correct answer. Justification:

A. User management assumes ownership of the project and resulting system, allocates
qualified

representatives to the team and actively participates in system requirements definition,
acceptance testing and user training. User management should review and approve system
deliverables as they are defined and accomplished, or implemented.

B. . A project steering committee provides overall direction, ensures appropriate
representation of the

major stakeholders in the project's outcome, reviews project progress regularly and holds
emergency meetings when required. A project steering committee is ultimately responsible
for all deliverables, project costs and schedules.

C. Senior management demonstrates commitment to the project and approves the
necessary resources to complete the project. This commitment from senior management
helps ensure involvement by those who are needed to complete the project.

D. Quality assurance staff review results and deliverables within each phase, and at the end
of each phase confirm compliance with standards and requirements. The timing of reviews
depends on the system development life cycle, the impact of potential deviation
methodology used, the structure and magnitude of the system and the impact of potential
deviation.




1

,A3-2 Which of the following BEST helps to prioritize project activities and determine the
time line for a project?



A. A Gantt chart

B. Earned value analysis

C. Program evaluation review technique

D. Function point analysis - ANSWER C is the correct answer. Justification:

A. A Gantt chart is a simple project management tool and would help with the prioritization
requirement, but it is not as effective as program evaluation review technique (PERT).

B. Earned value analysis is a technique to track project cost versus project deliverables but
does not assist in prioritizing tasks.

C. The PERT method works on the principle of obtaining project time lines based on project
events for three likely scenarios-worst, best and normal. The timeline is calculated by a
predefined formula and identifies the critical path, which identifies the key activities that
must be prioritized.

D. Function point analysis measures the complexity of input and output and does not help to
prioritize project activities.



A3-3 An IS auditor reviewing a series of completed projects finds that the implemented
functionality often exceeded requirements and most of the projects ran significantly over
budget. Which of these areas of the organization's project management process is the MOST
likely cause of this issue?



A. Project scope management

B. Project time management

C. Project risk management

D. Project procurement management - ANSWER A is the correct answer. Justification:

A. Because the implemented functionality is greater than what was required, the most likely
cause of the budget issue is failure to effectively manage project scope. Project scope
management is defined as the processes required to ensure that the project includes all of
the required work, and only the required work, to complete the project.




2

,B. Project time management is defined as the processes required to ensure timely
completion of the

project. The issue noted in the question does not mention whether projects were completed
on time, so this is not the most likely cause.

C. Project risk management is defined as the processes concerned with identifying, analyzing
and responding to project risk. Although the budget overruns mentioned above represent
one form of project risk, they appear to be caused by implementing too much functionality,
which relates more directly to project scope.

D. Project procurement management is defined as the processes required to acquire goods
and services from outside the performing organization. Although purchasing goods and
services that are too expensive can cause budget overruns, in this case the key to the
question is that implemented functionality is greater than what was required, which is more
likely related to project scope.



A3-4 An IS auditor is reviewing the software development process for an organization. Which
of the following functions are appropriate for the end users to perform?



A. Program output testing

B. System configuration

C. Program logic specification

D. Performance tuning - ANSWER A is the correct answer. Justification:

A. A user can test program output by checking the program input and comparing it with the

system output. This task, although usually done by the programmer, can also be done
effectively by the user.

B. System configuration is usually too technical to be accomplished by a user and this
situation could

create security issues. This could introduce a segregation of duties issue.

C. Program logic specification is a very technical task that is normally performed by a
prqgrammer. This could introduce a segregation of duties issue. . .

D. Performance tuning also requires high levels of technical skill and will not be effectively
accomplished by a user. This could introduce a segregation of duties issue.




3

, A3-5 An IS auditoris reviewing system developmentfor a health care organizationwith two
application environments production and test. During an interview,the auditor notes that
production data are used in the test environment to test program changes.What is the MOST
significant potential risk from this situation?



A. The test environment may not have adequate controls to ensure data accuracy.

B. The test environment may produce inaccurate results due to use of production data.

C. Hardware in the test environment may not be identical to the production environment.

D. The test environment may not have adequate access controls implemented to ensure
data confidentiality. - ANSWER D is the correct answer. Justification:

A. The accuracy of data used in the test environment is not of significant concern as long as
these data

are representative of the production environment.

B. Using production data in the test environment does not cause test results to be
inaccurate. If anything, using production data improves the accuracy of testing processes,
because the data most closely

mirror the production environment. In spite of that fact, the risk of data disclosure or
unauthorized access in the test environment is still significant and, as a result, production
data should not be used in the test environment. This is especially important in a health care
organization where patient data

confidentiality is critical and privacy laws in many countries impose strict penalties on
misuse of these

data.

C. Hardware in the test environment shouldmirror the production environment to ensure
that testing is reliable. However, this does not relate to the risk from using live data in a test
environment. This is not the correct answer because it does not relate to the risk presented
in the scenario.

D. In many cases, the test environment is not configured with the same access controls that
are

enabled in the production environment. For example, programmers may have privileged
access to the test environment (for testing), but not to the production environment. If the
test environment does not have adequate access control, the production data are subject to
risk of unauthorized access and/or data disclosure. This is the most significant risk of the
choices listed.

4

Document information

Uploaded on
February 20, 2026
Number of pages
103
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$19.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
THESTUDYVAULT
3.4
(20)
Sold
157
Followers
6
Items
14231
Last sold
2 days ago




Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions