What is a Contracting Officer Representative?
A technical representative that is appointed by the contracting officer through a designation letter
The procuring Contracting Officer, Administrative Contracting Officer, Termination Contracting Officer,
and the Contracting Officer's Representative are key players in the acquisition process. From the
following statements, choose the correct answer:
The contracting officer appoints the contracting officer's representative in writing
In your position as a COR, Conflict of Interest rules and regulations prohibit you from:
Working on a government matter that has an effect on your personal financial interests
The contractor gives a federal employee tickets to a local production of a Broadway play. The tickets are
worth $20. Was an ethics law or regulation violated? If so, which one?
No ethics law or regulation has been violated; however the appearance of impropriety might exist
When writing a SOW use the SMART principle which stands for:
Specific, Measurable, Accountable, Reasonable, Time-Based
2/10/2026
All of the following are elements of a Purchase Request EXCEPT________.
COR nomination letter
1
, CLC 222 CONTRACTING EXAM 2026/2027|QUESTIONS AND
02/10/2026
CORRECT ANSWERS LATEST EXAM
The purpose of evaluation factors is to represent the key areas of importance and emphasis to be
considered in the source selection decision. Of the statements below, the only true statement is:
The offeror can be evaluated against the evaluation factors and compared to other offerors' proposals
What are the differences between contracting by negotiation and sealed bidding?
Negotiation allow for communication and evaluation factor tradeoffs with the contractor
Elements of a Market Research report include: (Select all that apply)
1. Product or service characterized
2. Available sources
3. Pricing
What is an Independent Government Estimate (IGE)?
An independent detailed assessment developed by a government team member...
A Statement Of Work should include the following:
The work to be performed, location of work, period of performance, deliverable schedule, any special
requirements
Acquisition Planning's principal purpose is to ensure that the government meets its needs in the most
2/10/2026
effective, economical and timely manner while emphasizing competition and promoting the use of
commercial items.
2
, CLC 222 CONTRACTING EXAM 2026/2027|QUESTIONS AND
02/10/2026
CORRECT ANSWERS LATEST EXAM
True
The COR's role in evaluating and awarding a contract include IPT member, SSEB technical evaluator, and
Technical Expert or Representative.
True
The two techniques used to select a contractor within the best value continuum include:
Lowest price technically available and trade off process
Who has the official responsibility for performing market research?
COR/functional office
Items to consider during the development of the IGE include: (select all that apply)
1. An estimate that agrees with document market research
2. an unbiased realistic cost estimate for supplies or services that will be procured under the contract
The existing contract, including all options, is about to end. The customer likes the work of the
incumbent contractor and has expressed a desire to have the new contract be awarded to that
incumbent contractor. Which one of the following statements is true?
The COR can assist an acquisition planning and writing the evaluation criteria to ensure the best
contractor is selected for the new contract