100% satisfaction guarantee Immediately available after payment Read online or as PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

Construction Management Practice Test Questions and Correct Answers

Rating
-
Sold
-
Pages
31
Grade
A+
Uploaded on
31-01-2026
Written in
2025/2026

Construction Management Practice Test Questions and Correct Answers

Institution
Construction Management
Module
Construction Management

Content preview

Construction Management Practice Test Questions and Correct
Answers
Question 1
Based on the guide quantity of 100 CY on a bid document for rock excavation, a contractor bid a unit price of $20/CY. If
the owner's representative determined that the contractor excavated 85 CY of rock during construction, how much will the
contractor get paid?
(a). $2000
(b). $1700
(c). $300
(d). $1800
Correct Answer
(b)




Page 1 of 31

,Question 2
Which of the following documents are included in the bid package?
I. Proposal Form
II. Special Conditions
III. Technical Specifications
IV. General Conditions
V. Bid Bond
(a). I, II, and III
(b). II, III, and IV
(c). I, II, IV, and V
(d). I, II, III, and IV
Correct Answer
(d)



Question 3
The document requested by the owner as a protection against the risk of the contractor not accepting the job once
awarded the project is
(a). Insurance
(b). Performance Bond
(c). Bid Bond
(d). Payment Bond
Correct Answer
(c)




Page 2 of 31

,Question 4
Which of the following would not be considered an excusable delay?
(a). Labor Strikes
(b). Review process delays
(c). A hurricane closing a port delaying delivery of materials
(d). Death of a contractor
Correct Answer
(b)



Question 5
The typically 30-90 days period after the bid opening where the contractor is bound by their bid is called
(a). Acceptance period
(b). Bid period
(c). Anxiety period
(d). Risk period
Correct Answer
(a)




Page 3 of 31

, Question 6
The procedure that allows a contractor to propose changes to the design with the approval of the designer to save time
and/or money is called
(a). Process Engineering
(b). Value Engineering
(c). Design build engineering
(d). Cost engineering
Correct Answer
(b)



Question 7
Which of the following documents determines the zero day of the project for scheduling purposes?
(a). Proposal Form
(b). Formal contract
(c). Notice to bidders
(d). Notice to proceed
Correct Answer
(d)




Page 4 of 31

Written for

Institution
Construction Management
Module
Construction Management

Document information

Uploaded on
January 31, 2026
Number of pages
31
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorExpert West Virgina University
View profile
Follow You need to be logged in order to follow users or courses
Sold
487
Member since
3 year
Number of followers
313
Documents
8722
Last sold
3 days ago

Expertise in Nursing, Biochemistry, Mathematics, Psychology, Biology, History etc. My Work contains the latest, updated Exam Solutions, Study Guides.100% verified & Guarantee Top Grades Attained.

3.7

63 reviews

5
27
4
12
3
11
2
2
1
11

Trending documents

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions