PM/490: PROJECT MANAGEMENT CAPSTONE WK 4 -
PRACTICE: WEEK 4 QUICK CHECK QUESTIONS AND
ANSWERS WITH VERIFIED SOLUTIONS 100%
In a change request, that is a corrective action? -
ANSWER A planned action that brings the project back
into alignment with the project management plan
What should be submitted when an issue arises that
requires modification to the project? - ANSWER Change
request
What information may be included in the issue log? -
ANSWER All of the above
Which of the following documents is an input to Baseline
Tracking? - ANSWER Project schedule
What is the purpose of baselining? - ANSWER To track
actual project results against the plan
PRACTICE: WEEK 4 QUICK CHECK QUESTIONS AND
ANSWERS WITH VERIFIED SOLUTIONS 100%
In a change request, that is a corrective action? -
ANSWER A planned action that brings the project back
into alignment with the project management plan
What should be submitted when an issue arises that
requires modification to the project? - ANSWER Change
request
What information may be included in the issue log? -
ANSWER All of the above
Which of the following documents is an input to Baseline
Tracking? - ANSWER Project schedule
What is the purpose of baselining? - ANSWER To track
actual project results against the plan