What is the purpose of buffers in scheduling? - ANSWER-Buffers are built
between chains of continuously progressing construction activities to manage
time or distance intervals.
What is the difference between resource smoothing and resource leveling? -
ANSWER-Resource smoothing reduces resource usage without delaying the
project, while resource leveling may delay the project to keep resource usage
below a maximum.
What is crashing in project management? - ANSWER-Crashing is a technique
used to shorten a schedule by assigning additional resources to critical path
tasks.
What is the difference between accelerating and crashing activities? -
ANSWER-Accelerating reduces activity time, while crashing is the shortest
possible time achieved through additional resources.
What is the range of error for a detailed estimate according to AACE? -
ANSWER-The range of error for a detailed estimate is typically less than 10%.
,What factors influence early estimates in project management? - ANSWER-
Factors include thoroughness of scope, expected level of detail and accuracy,
and past market conditions.
What is the purpose of contingency in bidding estimates? - ANSWER-
Contingency is added to the base estimate to account for risk and uncertainty.
What are cost centers in estimating? - ANSWER-Cost centers are
subcomponents of the project used for cost estimation, such as walls, floors, and
roofs.
What is the purpose of quantity takeoff in estimating? - ANSWER-Quantity
takeoff determines the quantities of work in appropriate units for accurate cost
estimation.
What is the significance of the Work Breakdown Structure (WBS) in
estimating? - ANSWER-WBS helps identify work packages and subdivide them
into identifiable tasks for accurate estimation.
What is the formula for calculating the base estimate in project management? -
ANSWER-Base Estimate = Sum of (Work Package estimates + Work Package
contingency).
How does the City Cost Index affect estimating? - ANSWER-It adjusts costs
based on regional differences, allowing for more accurate cost projections.
What is the role of historical data in estimating project costs? - ANSWER-
Historical data provides a basis for pricing quantities and helps improve the
accuracy of estimates.
,What is the impact of market conditions on project costs? - ANSWER-Market
conditions can influence costs, leading to adjustments in estimates based on
supply and demand.
What are the three elements to consider in project management? - ANSWER-
Cost incurred to date, work actually completed, and current schedule.
What is the easiest method to measure project progress? - ANSWER-Costs
incurred.
What is a common challenge in the relationship between cost and results in
project management? - ANSWER-There is no set relationship between cost and
results; projects may incur costs with disproportionate results.
What are the four views of project status? - ANSWER-1. Over Budget and
Behind Schedule (Normal and Likely), 2. Under Budget and Behind Schedule
(Common), 3. Over Budget and Ahead of Schedule (Common), 4. Under
Budget and Ahead of Schedule (Rare and Not Likely).
What is the Units Method in measuring work? - ANSWER-A method
measuring pieces of work requiring similar amounts of effort.
What are Incremental Milestones in project management? - ANSWER-Any
work item involving parts that must be handled in sequence.
What does the Start and Finish method involve? - ANSWER-Using any work
item where it's easy to measure or compute a percentage of completion.
What is the Cost Ratio method used for? - ANSWER-It is used on
administrative tasks that are active over the life of the project.
, What are some effects that can impact the final outcome of a project? -
ANSWER-Equipment failure, rainy days, and other unforeseen circumstances.
What is the significance of the relationship between time, cost, and results? -
ANSWER-There is no set relationship between cost and results and elapsed
time.
What does it indicate if, on day 8 of a project, 55% of the budget has been spent
while only 47% was planned? - ANSWER-The project is 8% over budget.
What does it mean if a project is 7% ahead of schedule? - ANSWER-The
project has completed 57% of work while only 50% was planned by day 8.
What is a key control issue at the beginning of a project? - ANSWER-
Achieving maximum productivity soon after start-up to avoid losing
unrecoverable time.
What is the significance of predecessors and successors in project scheduling? -
ANSWER-Predecessors are tasks that must be completed before another can
start, while successors are tasks that cannot start until a prior task is completed.
What is the function of a Bar Chart in project scheduling? - ANSWER-Displays
the schedule for the entire project, breaking it down into a manageable number
of tasks.
What does the Circle notation represent in Activity on Node (AON) diagrams? -
ANSWER-Each circle represents a task.
What is a Dummy Activity in project scheduling? - ANSWER-A dummy arrow
used in AON diagrams to eliminate the need for extraneous relationships; it is
represented as a dotted arrow with zero duration.