DBIA Practice Exam Questions And Correct
Answers (Verified Answers) Plus Rationales
2026 Q&A | Instant Download Pdf
1. The primary purpose of design-build delivery is to:
A. Separate design and construction responsibilities
B. Integrate design and construction under a single contract
C. Eliminate contractor involvement in design
D. Delay project delivery
Design-build combines design and construction responsibilities to
improve collaboration and efficiency.
2. In design-build, the owner’s single point of responsibility is the:
A. Architect
B. Design-builder
C. Construction manager
D. Owner’s representative
The design-builder holds contractual responsibility for both design
and construction.
3. Which phase typically occurs first in a design-build project?
A. Construction
B. Commissioning
C. Conceptual design
D. Warranty period
Conceptual design lays out the initial project vision and scope.
,4. A Guaranteed Maximum Price (GMP) contract ensures that the:
A. Owner pays actual cost only
B. Price will not exceed an agreed limit
C. Designer controls budget changes
D. Contractor’s profit is unknown
A GMP sets a cap on the project cost, protecting the owner from
overruns.
5. In design-build procurement, qualifications are typically evaluated:
A. After price proposals
B. Before price proposals
C. Only for subcontractors
D. Never evaluated
Qualifications-based selection focuses first on capability and
experience.
6. The design-builder assumes risk for:
A. Owner’s financing
B. Design errors and construction performance
C. Zoning approvals
D. Environmental compliance only for owners
Design-builders manage risks associated with design and
construction integration.
7. Best Value Selection (BVS) in design-build emphasizes:
A. Lowest bid only
B. Balance of qualifications and price
C. Qualifications only
D. Random selection
BVS considers both experience and cost for award decisions.
, 8. Performance specifications in design-build:
A. Dictate exact materials
B. Define required outcomes
C. Are optional in all contracts
D. Eliminate owner requirements
Performance specs describe what the project must achieve, not
how.
9. Which of the following is a key benefit of design-build?
A. Increased change orders
B. Faster project delivery
C. Longer dispute resolution
D. Fragmented communication
Design-build fosters collaboration, often reducing schedule
durations.
10. The “bridging” design approach refers to:
A. Full design documents provided by owner
B. Preliminary design provided by owner
C. No design involvement by owner
D. Contractor selects designer
Bridging gives a starting point while still allowing design-builder
innovation.
11. A Request for Qualifications (RFQ) does NOT typically
include:
A. Experience requirements
B. Final price proposals
C. Project description
Answers (Verified Answers) Plus Rationales
2026 Q&A | Instant Download Pdf
1. The primary purpose of design-build delivery is to:
A. Separate design and construction responsibilities
B. Integrate design and construction under a single contract
C. Eliminate contractor involvement in design
D. Delay project delivery
Design-build combines design and construction responsibilities to
improve collaboration and efficiency.
2. In design-build, the owner’s single point of responsibility is the:
A. Architect
B. Design-builder
C. Construction manager
D. Owner’s representative
The design-builder holds contractual responsibility for both design
and construction.
3. Which phase typically occurs first in a design-build project?
A. Construction
B. Commissioning
C. Conceptual design
D. Warranty period
Conceptual design lays out the initial project vision and scope.
,4. A Guaranteed Maximum Price (GMP) contract ensures that the:
A. Owner pays actual cost only
B. Price will not exceed an agreed limit
C. Designer controls budget changes
D. Contractor’s profit is unknown
A GMP sets a cap on the project cost, protecting the owner from
overruns.
5. In design-build procurement, qualifications are typically evaluated:
A. After price proposals
B. Before price proposals
C. Only for subcontractors
D. Never evaluated
Qualifications-based selection focuses first on capability and
experience.
6. The design-builder assumes risk for:
A. Owner’s financing
B. Design errors and construction performance
C. Zoning approvals
D. Environmental compliance only for owners
Design-builders manage risks associated with design and
construction integration.
7. Best Value Selection (BVS) in design-build emphasizes:
A. Lowest bid only
B. Balance of qualifications and price
C. Qualifications only
D. Random selection
BVS considers both experience and cost for award decisions.
, 8. Performance specifications in design-build:
A. Dictate exact materials
B. Define required outcomes
C. Are optional in all contracts
D. Eliminate owner requirements
Performance specs describe what the project must achieve, not
how.
9. Which of the following is a key benefit of design-build?
A. Increased change orders
B. Faster project delivery
C. Longer dispute resolution
D. Fragmented communication
Design-build fosters collaboration, often reducing schedule
durations.
10. The “bridging” design approach refers to:
A. Full design documents provided by owner
B. Preliminary design provided by owner
C. No design involvement by owner
D. Contractor selects designer
Bridging gives a starting point while still allowing design-builder
innovation.
11. A Request for Qualifications (RFQ) does NOT typically
include:
A. Experience requirements
B. Final price proposals
C. Project description