ISTQB Test Manager (Syllabus) Questions and
answers 100% PASS
b) Identification of external web services and enforcement of service level
agreements (SLAs) with service provider done by project management and test
management.
c) Integration test level plan defined by test manager before each development
cycle and handed over to developers on day 10 - CORRECT ANSWER-You are
the Test Manager working on a project developing a tourist information mobile
application. The project recently switched to an agile process and test-driven
development. Each development cycle
lasts 15 days, with daily builds beginning at day 7. After day 10, no new features are
allowed to be added. The development team is composed of very experienced
team members, who are proud of their work, but not tolerant of the testing team.
The requirements are written down as coarse-grained user stories like the following
one:
,The software depends on existing web services, which are stubbed during
development. Unit testing is done by developers, while system and user acceptance
testing is the testing team's responsibility. System test in earlier development cycles
was often blocked due to severe failures of newly developed features. Analysis
shows that many of these failures could have been found during unit test. Analysis
of issues found during production show that 30% of performance problems were
due to unreliable web services delivered by 3rd party suppliers. Primary test
objectives are to mitigate the perceived performance risks and to increase the
confidence that no failures with high severity will occur in user stories with priority
>= High. Moreover, upper management demanded for closer cooperation of
testers and developers.
Which of the following test activities and/or work products will achieve the test
objectives best?
a) Approval of detailed design specifications by inspections done by the test team
before day 7, when the daily builds begin.
b) Identification of external web services and enforcement of service level
agreements (SLAs) with service provider done by project management and test
management.
c) Integration test level plan defined by test manager before each development
cycle and handed over to deve
© 2026 Copyright. All Rights Reserved. This document is
protected by copyright law
,A - CORRECT ANSWER-You are the Test Manager working on a project
developing a tourist information mobile application. The project recently switched
to an agile process and test-driven development. Each development cycle
lasts 15 days, with daily builds beginning at day 7. After day 10, no new features are
allowed to be added. The development team is composed of very experienced
team members, who are proud of their work, but not tolerant of the testing team.
The requirements are written down as coarse-grained user stories like the following
one:
The software depends on existing web services, which are stubbed during
development. Unit testing is done by developers, while system and user acceptance
testing is the testing team's responsibility. System test in earlier development cycles
was often blocked due to severe failures of newly developed features. Analysis
shows that many of these failures could have been found during unit test. Analysis
of issues found during production show that 30% of performance problems were
due to unreliable web services delivered by 3rd party suppliers. Primary test
objectives are to mitigate the perceived performance risks and to increase the
confidence that no failures with high severity will occur in user stories with priority
>= High. Moreover, upper management demanded for closer cooperation of
testers and developers.
The following exit criteria for acceptance testing have been specified:
, AC 1: Software response time <= 3 sec for up to 1,000 simultaneous requests of
user stories with priority = Very High
AC 2: Software response time <= 10 sec for up to 10,000 simultaneous requests of
user stories with priority >= High
AC 3: No severe failure in system and user acceptance test of user stories with
priority >= High
AC 4: All user stories covered by at least one user acceptance test case
In the test strategy,
a) Test design and test execution is outsourced.
d) Test basis is of low quality. - CORRECT ANSWER-Which of the following
factors indicate most that detailed test conditions should be specified for system
testing?
a) Test design and test execution is outsourced.
b) Test basis is changing frequently.
c) Domain experts are available for consultation during test design.
d) Test basis is of low quality.
e) Test conditions are used for management milestone presentations.
Select TWO options.
© 2026 Copyright. All Rights Reserved. This document is
protected by copyright law
answers 100% PASS
b) Identification of external web services and enforcement of service level
agreements (SLAs) with service provider done by project management and test
management.
c) Integration test level plan defined by test manager before each development
cycle and handed over to developers on day 10 - CORRECT ANSWER-You are
the Test Manager working on a project developing a tourist information mobile
application. The project recently switched to an agile process and test-driven
development. Each development cycle
lasts 15 days, with daily builds beginning at day 7. After day 10, no new features are
allowed to be added. The development team is composed of very experienced
team members, who are proud of their work, but not tolerant of the testing team.
The requirements are written down as coarse-grained user stories like the following
one:
,The software depends on existing web services, which are stubbed during
development. Unit testing is done by developers, while system and user acceptance
testing is the testing team's responsibility. System test in earlier development cycles
was often blocked due to severe failures of newly developed features. Analysis
shows that many of these failures could have been found during unit test. Analysis
of issues found during production show that 30% of performance problems were
due to unreliable web services delivered by 3rd party suppliers. Primary test
objectives are to mitigate the perceived performance risks and to increase the
confidence that no failures with high severity will occur in user stories with priority
>= High. Moreover, upper management demanded for closer cooperation of
testers and developers.
Which of the following test activities and/or work products will achieve the test
objectives best?
a) Approval of detailed design specifications by inspections done by the test team
before day 7, when the daily builds begin.
b) Identification of external web services and enforcement of service level
agreements (SLAs) with service provider done by project management and test
management.
c) Integration test level plan defined by test manager before each development
cycle and handed over to deve
© 2026 Copyright. All Rights Reserved. This document is
protected by copyright law
,A - CORRECT ANSWER-You are the Test Manager working on a project
developing a tourist information mobile application. The project recently switched
to an agile process and test-driven development. Each development cycle
lasts 15 days, with daily builds beginning at day 7. After day 10, no new features are
allowed to be added. The development team is composed of very experienced
team members, who are proud of their work, but not tolerant of the testing team.
The requirements are written down as coarse-grained user stories like the following
one:
The software depends on existing web services, which are stubbed during
development. Unit testing is done by developers, while system and user acceptance
testing is the testing team's responsibility. System test in earlier development cycles
was often blocked due to severe failures of newly developed features. Analysis
shows that many of these failures could have been found during unit test. Analysis
of issues found during production show that 30% of performance problems were
due to unreliable web services delivered by 3rd party suppliers. Primary test
objectives are to mitigate the perceived performance risks and to increase the
confidence that no failures with high severity will occur in user stories with priority
>= High. Moreover, upper management demanded for closer cooperation of
testers and developers.
The following exit criteria for acceptance testing have been specified:
, AC 1: Software response time <= 3 sec for up to 1,000 simultaneous requests of
user stories with priority = Very High
AC 2: Software response time <= 10 sec for up to 10,000 simultaneous requests of
user stories with priority >= High
AC 3: No severe failure in system and user acceptance test of user stories with
priority >= High
AC 4: All user stories covered by at least one user acceptance test case
In the test strategy,
a) Test design and test execution is outsourced.
d) Test basis is of low quality. - CORRECT ANSWER-Which of the following
factors indicate most that detailed test conditions should be specified for system
testing?
a) Test design and test execution is outsourced.
b) Test basis is changing frequently.
c) Domain experts are available for consultation during test design.
d) Test basis is of low quality.
e) Test conditions are used for management milestone presentations.
Select TWO options.