CSI CDT Mock Exam Questions with

Correct Answers

The cost of materials plus and additional fee of overhead and profit. (Fee Negotiated), a GMP

(Guaranteed Maximum Price), shared savings (Split % 60/40 of Savings) and incentives for early

completion(Bonus) may all be part of a negotiated "Cost-Plus Fee".

Ref PDPG 7.1.6.3

Change Orders are:

A. Prepared by the Contractor.

B. Prepared by the Architect/Engineer.

C. Prepared by the Owner.

D. Prepared by any of the above. B. Prepared...