TSM 214 FINAL EXAM QUESTIONS AND ANSWERS

During the identify risk process, the project manager and the team categorize risks in an effort to

determine risks they may have missed. Of the following, which is the best example of risk categories?

a-Quality, schedule, budget

b-External, internal, technology, personnel

c-Scope, time, cost

d-Initiating, planning, executing, monitoring, and controlling, closing - CORRECT ANSWERb)

External, internal, technology, personnel