WGU C783 Exam 1 — Questions & Answers
NewWGU C783 Exam 1 — Questions & Answers 
Part A — Project Management Foundations 
1. A project is best defined as: 
A. An ongoing operation that repeats indefinitely 
B. A temporary endeavor undertaken to create a unique product, service or result 
C. Any routine business activity 
D. A department within an organization 
Answer: B. A temporary endeavor undertaken to create a unique product, 
service or result 
Rationale: Projects have a definite beginning and end. 
2. Which of the following is...
Exam (elaborations)
WGU C783 Final Exam — Questions & Answers
PopularWGU C783 Final Exam — Questions & Answers 
Part A — Foundations and Initiating Review 
1. The main purpose of project management is to: 
A. Apply knowledge, skills, tools and techniques to project activities to meet project 
requirements and deliver value 
B. Eliminate all risk 
C. Maximize documentation 
D. Replace operations 
Answer: A. Apply knowledge, skills, tools and techniques to project activities to 
meet project requirements and deliver value 
Rationale: Project management balances...
Exam (elaborations)
WGU C783 Exam 3 — Questions & Answers
NewWGU C783 Exam 3 — Questions & Answers 
Part A — Executing the Project 
1. Direct and Manage Project Work involves: 
A. Writing the charter 
B. Closing contracts 
C. Leading and performing the work defined in the project management plan and 
implementing approved changes 
D. Identifying stakeholders only 
Answer: C. Leading and performing the work defined in the project 
management plan and implementing approved changes 
Rationale: Deliverables and work performance data are key outputs. 
2. W...
Exam (elaborations)
WGU C783 Exam 2 — Questions & Answers
NewWGU C783 Exam 2 — Questions & Answers 
Part A — Cost Planning 
1. The cost management plan describes: 
A. How project costs will be planned, structured and controlled, including units, precision 
and control thresholds 
B. The detailed schedule 
C. The risk register 
D. The stakeholder register 
Answer: A. How project costs will be planned, structured and controlled, 
including units, precision and control thresholds 
Rationale: It is part of the project management plan. 
2. A rough order of...
Exam (elaborations)
WGU C783 Unit Tests 1–6 — Questions & 
Answers
NewWGU C783 Unit Tests 1–6 — Questions & 
Answers 
Unit Test 1 — Project Management Foundations and Initiating 
1. Operations differ from projects mainly because operations are: 
A. Ongoing and repetitive 
B. Temporary 
C. Unique 
D. Always smaller 
Answer: A. Ongoing and repetitive 
Rationale: Projects often create capabilities that operations then use. 
2. A project's temporary nature means that: 
A. It has a definite beginning and end, although its outputs may last long after 
B. It is ...
Exam (elaborations)
WGU C783 Midterm Exam — Questions & 
Answers
NewWGU C783 Midterm Exam — Questions & 
Answers 
Part A — Foundations and Initiating (Scenarios) 
1. A company wants to upgrade its network infrastructure across five offices by next June. 
This effort is best classified as: 
A. An operation, because networks are ongoing 
B. A project, because it is temporary and produces a unique result 
C. A portfolio 
D. A program office 
Answer: B. A project, because it is temporary and produces a unique result 
Rationale: Maintaining the network afterward ...