Exam (elaborations)
COSC 463 Exam 1 Questions With Correct Answers.
COSC 463 Exam 1 Questions With Correct Answers.
Exam (elaborations)
COSC 463 - Final Exam (with 100% Correct Solutions)
PopularScope, Time, Cost correct answers In a change order, what must always be taken into account? 
 
Direct and Constructive correct answers What are the 2 major categories of change? 
 
Direct Change correct answers A change that is directly made such as a formal change order, CCD or a field change. 
 
Field Change correct answers change that is done on site and a formal change order is done later. 
 
Constructive Change Directive correct answers What does CCD stand for? 
 
Defective plans/specs, Mi...
Exam (elaborations)
Cosc 463 Test 1, Safety Anne Exam Questions And Answers
NewCosc 463 Test 1, Safety Anne Exam Questions And Answers 
What Are The Osha 10: Tasks - Correct Answercpr, Aed, Harness, Fire
Exam (elaborations)
COSC 463 - Exam 2 Questions With Correct Answers.
COSC 463 - Exam 2 Questions With Correct Answers.
Exam (elaborations)
COSC 463 TAMU - McCloskey Exam 2 Questions With Correct Answers.
COSC 463 TAMU - McCloskey Exam 2 Questions With Correct Answers.
Exam (elaborations)
COSC 463- Law 1 Exam 1 Questions With Correct Answers.
COSC 463- Law 1 Exam 1 Questions With Correct Answers.
Exam (elaborations)
Cosc 463 Quastion And Answer 2024-2025(Grading A+)
Cosc 463 Quastion And Answer (Grading A+)
Exam (elaborations)
COSC 463 Exam 2 (A+ Graded Already)
Prime Contractor, Subcontractors, Suppliers correct answers Successful project performance depends on the legal and business relationship among the _________ and _______ and _____ as much as any other factor 
 
Prime Contractor correct answers Party responsible to the owner for the satisfactory and timely completion of the project 
 
Subcontractor correct answers Party responsible for performing much of the work 
 
Price correct answers Disputes at the Bidding Stage: 
 
Disputes dealing with pri...
Exam (elaborations)
COSC 463 Exam 1 (with 100% Errorless Answers)
Contract correct answers Law dealing with a set of promises made by one party to another, the breach or upholding of that particular set of promises 
 
Breach of Contract correct answers When one party fails to execute what they agreed upon, without justification or reason 
 
Breach of Contract correct answers In a situation where a contractor fails to use the specified trim paint color, or its failure to complete the work on time, what has taken place? 
 
Express obligations correct answers Obl...
Exam (elaborations)
COSC 463 Exam 1 (100% Accurate Answers)
FIRAC correct answers Facts- the court will tell you the relevant facts. Your first paragraph in the paper should layout the facts. Write about it as if Ellis has never read the case. 
Issue- put in a question format. "is the defendant guilty of criminal negligence?" you cannot put all of your issues together, one issue at a time then list RAC then begin with a new issue 
Rule- law (case law, statute, agency rule, common law) 
Argument- analysis of facts with the law 
Conclusion- answer the i...
Exam (elaborations)
COSC 463 Exam 1 (All Correct 100%)
Civil Law correct answers law of private rights and duties that are used to resolve disputes between parties 
 
Criminal Law correct answers law that defines crimes against the public order and protects property owners against those who might try and take it or harm those on it 
 
Common Law correct answers standard of rules accepted by the public that changes with society using precedents set forth in judicial hearings throughout time 
 
Statutory Law correct answers laws passed by legislatures...
Exam (elaborations)
COSC 463 - Exam 1 (with Complete Solutions)
The contract is the document that generally governs the distribution of risk in the project. correct answers True 
 
What is the purpose of risk management? correct answers to reduce or eliminate the risks associated with financial loss 
 
What are the three techniques of risk management? correct answers manage assumption and retention of risk, loss control to prevent both the frequency of occurrence and the severity of losses, and the transfer of risk to a third party. 
 
Risk management: manag...
Exam (elaborations)
COSC 463 Exam 1 (100% Errorless Answers)
What is the Law? correct answers the minimum standard of behavior that a society will tolerate 
 
What are Ethics? correct answers going above and beyond the law, higher standard of behavior than for the law 
 
Are Law and Ethics the same thing? correct answers no, they are not equal to eachother 
 
What are the 4 types of laws? correct answers constitutions, statutory, common law, administrative 
 
Who are the parties in a criminal case? correct answers state vs. individual 
 
Who are the parti...
Exam (elaborations)
COSC 463 - Exam #2 – Daigneault (A+ Guaranteed)
James T. Taylor V. Arlington ISD: What are the key terms in this case? correct answers -Remedial mistake 
-Equitable relief 
-Negligence 
-Gross negligence 
-Unilateral mistake 
 
Remedial mistake conditions: correct answers a) the mistake is of so great a consequence that to enforce the contract made would be unconscionable. 
b) the mistake relates to a material feature of the contract 
C) the mistake must have been made regardless of the exercise of ordinary care 
D) the parties can be placed ...
Exam (elaborations)
COSC 463 - Exam 2 – Ellis (All Solved Correctly)
time allowed for contractors to see the bid and to be able to put together a bid. correct answers Sufficient Bid Advertising 
 
A time where anyone can see what the bids correct answers Public Reading 
 
According to bid statutes, contract is always awarded to what kind of bidder? correct answers lowest, responsive, responsible 
 
(T/F) Each characteristic in the term "lowest, responsive, responsible" bidder, all have the same amount of importance correct answers true 
 
Ensures the owner/cont...
Exam (elaborations)
COSC 463 Exam #2 (100% Correct Answers)
excusable correct answers excusable or non-excusable? acts of God 
 
unforeseen, price correct answers The Contractor shall perform _________________ work, for which there is no ____________ included in the contract, whenever it is necessary or desirable in order to complete fully the work as contemplated 
 
the contractor correct answers who normally bears the risk under a fixed price contract? 
 
Differing Site Conditions (Clause) correct answers NO IMPLIED RIGHT TO RECEIVE ADDITIONAL COMPENSA...
Exam (elaborations)
COSC 463 (A+ Guaranteed)
which set of laws is more strict, commercial or residential? correct answers residential 
 
does a contract always have to be in writing? correct answers no 
 
duty correct answers assigned by society, sometimes law 
common law 
 
common law correct answers common set of laws that all are obliged to observe 
 
can a contract violate a law correct answers no 
 
essential elements of construction contract correct answers offer 
acceptance 
meeting of minds 
communication of consent 
execution and ...
Exam (elaborations)
COSC 463 CHAPTER 7 (100% Correct Answers)
Historically, what were most public construction projects awarded using? correct answers competitive bidding process (sealed bids) 
 
In the last decade, new legislation has given many public agencies the flexibility to award contracts using the traditional sealed bid process or a competitive negotiation process. Competitive negotiation is awarded based on? correct answers best value to the owner 
 
What are the basic goals of the competitive negotiation process? correct answers to provide the p...
Exam (elaborations)
COSC 463 Test 1, Safety Anne (100% Accurate)
What are the OSHA 10: Tasks correct answers CPR, AED, HARNESS, FIRE 
 
What is PPE stand for? correct answers Personal Protection Equipment; Exposure Control 
 
What characteristics must one have in order to be safe? correct answers Awareness and Vilgilant 
 
Who is the most important person on the job site? correct answers Me, Myself, and I 
 
When was the Code of Federal Regulations for OSHA implemented? correct answers CFR 1910 
 
When was a Code of Federal Regulations created by OSHA specifi...
Exam (elaborations)
COSC 463 Test #2 Chapter 13 (100% Verified)
Owners include provisions that protect them in the event of a delay, these include correct answers Liquidated Damages Clauses 
Default 
Termination Clauses 
 
Contract Clauses that excuse the contractor/sub from certain delays include correct answers Force Majeure Clause 
Scheduling Clause 
Time extension Clause 
Changes Clause 
Claims Clause 
 
CPM (Critical Path Method) correct answers is a detailed mathematical model of construction plan that generally requires computes to manage and impl...