70+ PMP Exam Questions and Answers with Explanation
Q1. A project manager is informed that a key stakeholder is dissatisfied with the project outcomes. 
What should the project manager do first? 
A. Meet with the key stakeholder to better understand their concerns 
B. Update the lessons learned documentation with the new information 
C. Present the concerns at the next team meeting to get feedback 
D. Revise the project management plan to address the concerns 
Answer: A 
Explanation: The first thing a project manager should do when learning of a ...