NCCCO TELESCOPIC BOOM CRANES -SWING CAB(TLL)
WHEN WORKING AT GROUND NEAR A CELLAR WALL, WHERE SHOULD THE CRANES OUTRIGGER PADS BE PLACED? 
AT LEAST AS FAR BACK AS THE DEOTH OF THE WALL BELOW GROUND 
WHAT IS THE REQUIRED SET UP DISTANCE AWAY FROM EDGE OF SOFT OR SANDY EXCAVATED AREAS? 
1.5 TIMES DEPTH OF EXCAVATION AWAY FROM EDGE 
UPON ARRIVAL ON A NEW JOB SITE WITH A TRUCK CRANE, THE PRIMARY MAJOR CONCERN IS: 
UNDER GROUND UTILITIES 
DUNNAGE OR OUTRIGGER PADS MUST BE A MINIMUM OF _____________TIMES LARGER THAN THE FLOAT 
3 
WHEN ARRIVING I...
- Exam (elaborations)
- • 5 pages •
WHEN WORKING AT GROUND NEAR A CELLAR WALL, WHERE SHOULD THE CRANES OUTRIGGER PADS BE PLACED? 
AT LEAST AS FAR BACK AS THE DEOTH OF THE WALL BELOW GROUND 
WHAT IS THE REQUIRED SET UP DISTANCE AWAY FROM EDGE OF SOFT OR SANDY EXCAVATED AREAS? 
1.5 TIMES DEPTH OF EXCAVATION AWAY FROM EDGE 
UPON ARRIVAL ON A NEW JOB SITE WITH A TRUCK CRANE, THE PRIMARY MAJOR CONCERN IS: 
UNDER GROUND UTILITIES 
DUNNAGE OR OUTRIGGER PADS MUST BE A MINIMUM OF _____________TIMES LARGER THAN THE FLOAT 
3 
WHEN ARRIVING I...
Crane Core Practice Test
(D) Reduced stability - (D) Reduced stability 
Which of the following matches the appropriate load chart to a particular crane? 
(A) Serial number 
(B) Model number 
(C) Make of crane 
(D) Make & model number - (A) Serial number 
A durable rating chart with legible letters and figures shall be provided with each crane and attached in a location accessible to: 
(A) The site safety supervisor 
(B) The lift director 
(C) The project engineer 
(D) The operator while at the controls - (D) The operato...
- Exam (elaborations)
- • 48 pages •
(D) Reduced stability - (D) Reduced stability 
Which of the following matches the appropriate load chart to a particular crane? 
(A) Serial number 
(B) Model number 
(C) Make of crane 
(D) Make & model number - (A) Serial number 
A durable rating chart with legible letters and figures shall be provided with each crane and attached in a location accessible to: 
(A) The site safety supervisor 
(B) The lift director 
(C) The project engineer 
(D) The operator while at the controls - (D) The operato...
NCCCO Mobile Crane Core
Mobile Cranes (ASME) 
B30.5 
Slings (ASME) 
B30.9 
Hooks (ASME) 
B30.10 
Jack's (ASME) 
B30.1 
Personnel lifting systems (ASME) 
B30.23 
Tower Cranes (ASME) 
B30.3 
Rigging Hardware (ASME) 
B30.26 
Safety Devices (OSHA) 
1926.1415 
Operational Aids (OSHA)
- Exam (elaborations)
- • 33 pages •
Mobile Cranes (ASME) 
B30.5 
Slings (ASME) 
B30.9 
Hooks (ASME) 
B30.10 
Jack's (ASME) 
B30.1 
Personnel lifting systems (ASME) 
B30.23 
Tower Cranes (ASME) 
B30.3 
Rigging Hardware (ASME) 
B30.26 
Safety Devices (OSHA) 
1926.1415 
Operational Aids (OSHA)
NCCCO Telescopic Boom Crane
According to OSHA, how many randomly distributed broken wires in rotation-resistant rope is caused for taking the rope out of service - 2 broken wires in 6 rope diameters 
What would an operator use to determine boom tip height - Manufacturers working range diagram 
The lay length of a wire rope is defined as what - Distance it takes for 1 strand to make a complete revolution 
When reading regulations the word MUST is treated how - As mandatory 
What is the correct procedure when placing a shack...
- Exam (elaborations)
- • 12 pages •
According to OSHA, how many randomly distributed broken wires in rotation-resistant rope is caused for taking the rope out of service - 2 broken wires in 6 rope diameters 
What would an operator use to determine boom tip height - Manufacturers working range diagram 
The lay length of a wire rope is defined as what - Distance it takes for 1 strand to make a complete revolution 
When reading regulations the word MUST is treated how - As mandatory 
What is the correct procedure when placing a shack...
NCCCO Telescopic Boom Mobile Cranes
T or F 
The ground pressure under the outriggers is higher than it is under a crawler track because of the smaller bearing surface - True 
An outrigger float should be approximately how much larger that the outrigger pad? - 3 times 
When setting a a crawler crane for use on a new site, which of the following is not required prior to use? - name of the person that will operate the crane 
Where should the slings be attached when lifting lattice boom sections? - use the end connections 
T or F 
Dur...
- Exam (elaborations)
- • 11 pages •
T or F 
The ground pressure under the outriggers is higher than it is under a crawler track because of the smaller bearing surface - True 
An outrigger float should be approximately how much larger that the outrigger pad? - 3 times 
When setting a a crawler crane for use on a new site, which of the following is not required prior to use? - name of the person that will operate the crane 
Where should the slings be attached when lifting lattice boom sections? - use the end connections 
T or F 
Dur...
CCO PRACTICE EXAM
d)stop crane from sliding unexpectedly - increase the crane's stability when operating over front or back 
What quadrant produces the least amount of ground pressure on a lattice crawler: 
a) corner 
b) side 
c) front 
d) rear - side 
During assembly where should you attach slings to lift boom sections: 
a) to the top of main chords 
b) to the top end fittings 
c) 2 feet from end of section 
d) center of boom section - to the top end fittings 
When a lattice boom truck crane is set up on outr...
- Exam (elaborations)
- • 16 pages •
d)stop crane from sliding unexpectedly - increase the crane's stability when operating over front or back 
What quadrant produces the least amount of ground pressure on a lattice crawler: 
a) corner 
b) side 
c) front 
d) rear - side 
During assembly where should you attach slings to lift boom sections: 
a) to the top of main chords 
b) to the top end fittings 
c) 2 feet from end of section 
d) center of boom section - to the top end fittings 
When a lattice boom truck crane is set up on outr...
NCCCO CORE
On what principle is crane stability based? - leverage 
Who must confirm that an overhead power line is de-energized? - Line owner 
The use of equipment to hoist personnel is prohibited except where the employer can demonstrate what? - Other methods would be more hazardous 
Which of the following would not cause the effect of impact loading on the crane? 
A. Sudden snatching of the load 
B. Rapid hoist acceleration 
C. High boom angle operations in windy conditions 
D. Graduated lever control ap...
- Exam (elaborations)
- • 9 pages •
On what principle is crane stability based? - leverage 
Who must confirm that an overhead power line is de-energized? - Line owner 
The use of equipment to hoist personnel is prohibited except where the employer can demonstrate what? - Other methods would be more hazardous 
Which of the following would not cause the effect of impact loading on the crane? 
A. Sudden snatching of the load 
B. Rapid hoist acceleration 
C. High boom angle operations in windy conditions 
D. Graduated lever control ap...
NCCCO PREP
When is the hoist line on top of the boom considered part of the load? - It is not considered 
When a heavy load is lifted, what is the result? - Boom deflection 
According to OSHA 1926 Subpart CC, for cranes traveling with no load, what is the minimum clearance for energized power lines at 40kV? - 6ft 
Wich of the following rigging configurations is listed in order of the strongest to weakest? - Basket, Vertical, Choker 
According to OSHA 1926 Subpart CC, how many randomly distributed broken wi...
- Exam (elaborations)
- • 11 pages •
When is the hoist line on top of the boom considered part of the load? - It is not considered 
When a heavy load is lifted, what is the result? - Boom deflection 
According to OSHA 1926 Subpart CC, for cranes traveling with no load, what is the minimum clearance for energized power lines at 40kV? - 6ft 
Wich of the following rigging configurations is listed in order of the strongest to weakest? - Basket, Vertical, Choker 
According to OSHA 1926 Subpart CC, how many randomly distributed broken wi...
Crane Load Charts
Level to within 1% (0.57 degrees) and on a firm surface 
Ratings above the bold line, shaded or with an asterisk indicate _____. 
Loads in the structural portion of the load chart 
Ratings below the bold line, shaded or with an asterisk indicate _____. 
Loads in the stability portion of the load chart 
What happens if you exceed the structural capacities on a load chart? 
You may physically break a load bearing component. 
What happens if you exceed the stability based capacities on a load chart...
- Exam (elaborations)
- • 5 pages •
Level to within 1% (0.57 degrees) and on a firm surface 
Ratings above the bold line, shaded or with an asterisk indicate _____. 
Loads in the structural portion of the load chart 
Ratings below the bold line, shaded or with an asterisk indicate _____. 
Loads in the stability portion of the load chart 
What happens if you exceed the structural capacities on a load chart? 
You may physically break a load bearing component. 
What happens if you exceed the stability based capacities on a load chart...
Crane Operator
On wheel mounted cranes, the required distance to stop at 15 mph is: - 32 feet 
According to ASME B30.5, when working near power lines up to 350kV and the actual voltage level is not known how far must you stay away from the lines? - 20 feet 
OSHA and ASME regulations require any part of the crane to be how far from a 230kV power line? - 20 feet 
What would you do to prevent a load from swinging away from the crane when picking up a heavy load? - Raise the boom slightly to compensate for boom de...
- Exam (elaborations)
- • 13 pages •
On wheel mounted cranes, the required distance to stop at 15 mph is: - 32 feet 
According to ASME B30.5, when working near power lines up to 350kV and the actual voltage level is not known how far must you stay away from the lines? - 20 feet 
OSHA and ASME regulations require any part of the crane to be how far from a 230kV power line? - 20 feet 
What would you do to prevent a load from swinging away from the crane when picking up a heavy load? - Raise the boom slightly to compensate for boom de...