- Chapter 11 PMP Risk Management: Master the Processes, Inputs, Tools & Techniques for Exam Success 
 
 
 
1.	EMV Calculation for Estimated Project Cost Question: 
You have been asked to establish an estimated project cost using Expected Monetary Value (EMV). If the project has a best-case estimate of $10,000 with a probability of 20%, a most likely case estimate of $12,000 with a probability of 50%, and a worst-case estimate of $14,400 with a probability of 30%, what is the EMV for the project? 
...
-
$13.89 More Info