Project+ Study Guide: Exam PK0-004, 2nd Edition
Project+ Study Guide: Exam PK0-004, 2nd Edition 
Question 1 
(tb.ProjectPlSG2E.c05.07) 
Which of the following is true for float? 
A. It’s calculated by adding the durations of all tasks and dividing by the 
number of tasks. 
B. It’s time that you add to the project schedule to provide a buffer or 
contingency. 
D. It is calculated only on the longest path of the project schedule. 
 You Answered Correctly! 
Float time is the length of time a task may be started late or the additional dura...