COM 340 MIDTERM COMPLETE 4x4 Grid (capability and willingness) ANSWER = Can, Can't Will, Won't Can & will, Can't but will, Can but won't, Can't and won't Ideal size of a project team ANSWER = 5 or 7 members PERT Chart ANSWER = • A variat
COM 340 MIDTERM COMPLETE 
4x4 Grid (capability and willingness) 
ANSWER = Can, Can't 
Will, Won't 
Can & will, Can't but will, Can but won't, Can't and won't 
Ideal size of a project team 
ANSWER = 5 or 7 members 
PERT Chart 
ANSWER = • A variation of critical path analysis (CPM) 
• What is included: 
• Task Names (nodes) 
• Start dates 
• Estimated time to takes completion 
• Shortest, likely, and longest time 
• Calculate: shortest time + (4 x likely time) + longest time /6...