TEST BANK FOR PMI (PMP) EXAM 6TH EDITION PMBOK Chamberlain-college-nursing
-
---234December 20222022/2023A+
- An element of the project scope statement is: 
A. Acceptance criteria. 
B. A stakeholder list. 
C. A summary budget, 
D. High-level risks. 
Correct Answer: A 
QUESTION 2 
Which document describes the necessary information to determine if a project is worth the 
required investment? 
A. Cost baseline 
B. Service level agreement 
C. Memorandum of understanding 
D. Business case 
Correct Answer: D 
QUESTION 3 
Which input to the Plan Risk Management process provides information on high-level risks...
-