(Attempt=1/3)
Questions
Cost Analysis Exam
1) The term that consists of Development Cost plus Procurement Cost plus the cost of facilities
is:
Weapon System Cost
Life Cycle Cost
Program Acquisition Cost
Flyaway Cost
2) Which one of the following statements concerning an Analysis of Alternatives
is TRUE?
The AoA must be updated at all milestones including Milestone B and Full
Rate Production Decision
The Defense Acquisition Executive designates the activity who will prepare
the AoA for all ACAT ID, ACAT IC, ACAT II, and ACAT III programs
An AoA is required for both ACAT I and ACAT IA programs
The AoA is always prepared by the Program Manager and not by the User
Community
3) Which one of the following demonstrates the use of the CAIV philosophy?
Increasing the value of a system parameter so that it reaches its objective
level, even though it increases operating and support costs
Modifying a design to enhance system performance while making the
system more expensive to build and maintain
Increasing the development cost of a system to reduce operating and support
costs by a much larger amount
Delaying the program schedule to allow the development of technology that
will allow the program to reach the objective level of communications security
4) The following information pertains to the estimated number of labor hours required to
produce certain units of the WARTHOG system. What is the learning curve percentage
assumed by this data and how many labor hours will be required to produce the 160th unit?
,Unit Number Hours Required
10 2,000
10020 1,900 100
40 1,805 95
80 1,715 (90
160 1?
10% and 1,625
95% and 1,629
90% and 1,625
5% and 1,629
5) A life cycle cost estimate that is broken down by appropriation categories will:
mig_10106911 1
Include a category called RDT&E
Follow a product-oriented family tree structure
Include a category called Work Breakdown Structure (WBS)
Include a category called Product Improvement
6) Which one of the following parties is LEAST likely to review the Economic Analysis for an
ACAT IAM program?
Under Secretary of Defense for Policy (USD(P))
Overarching IPT
Defense Acquisition Board (DAB)
Information Technology Acquisition Board
7) Activity Based Costing can be used for which of the following purposes?
To set prices
All of the answers are correct
To identify product cost drivers
To identify opportunities for process improvement
8) What cost estimating technique would be most appropriate for the following situation?
Engineering and Manufacturing Development ( The estimate for a major system component is
due several months from now. So you have some time to develop the cost estimate. This
,component constitutes roughly 25 percent of the total system cost, so the estimate needs to be
very accurate and objective. The engineering design effort has completed the detailed design
drawings and the contractor has a detailed Work Breakdown Structure (WBS).
Analogy
Parametric
Actual Costs
Engineering
9) The life cycle cost of the BLUEBIRD system is $600 million. The program acquisition cost
is $400 million and the development cost is $150 million. There are no facilities costs. What is
the procurement cost of the BLUEBIRD system?
$200 million
$250 million
$150 million
$100 million
10) Budget authority is provided by an:
Expenditure
Obligation
Authorization
Appropriation
11) Which of the following statements about an ACAT ID program’s Life Cycle Cost Estimate
(LCCE) is FALSE?
The LCCE should be based upon information contained in the Cost Analysis
Requirements Description (CARD)
A program’s budget requests should be based on its LCCE
The LCCE must be updated at milestones A, B, C, Development Request for Proposals
(RPF) Release Decision (Dev RPF Rel), and the Full Rate Production Decision Review points
An Economic Analysis is a required portion of the LCCE
12) The method estimates costs from the bottom up using a detailed work
breakdown structure (WBS).
, Parametric
Analogy
Actual Cost
Engineering
) Which one of the following demonstrates the use of the CAIV philosophy?
Reducing the range of a Radar system from 500 nautical miles to 425 nautical miles to
reduce overall program cost.
Increasing the weight of the system such that it increases overall program cost.
Modifying a design to enhance system performance while making the system more
expensive to build and maintain
Delaying the program schedule to allow the maturation of technology
2) The document that lays out the specifications and assumptions to be used in preparing all
estimates of a program's cost is known as the:
Life Cycle Cost Estimate
Independent Cost Estimate
Cost Analysis Requirements Description (CARD)
Economic Analysis (EA)
3) Which of the following costs are included in the Total Ownership Cost (TOC)?
Research and Development
Operating and Support
Disposal
Investment
All of these are correct
4) Which of the following statements concerning Activity Based Costing (ABC) is TRUE?
ABC always allocates indirect and overhead costs equally across all products
ABC provides more accurate information about the real cost of a good or service than
traditional cost accounting