Which entity requires all employees be given information and training on the long
and short term health effects of the chemicals they work with? -correct answer OSHA
What type of fire extinguisher is required in the machine room? -correct answer ABC
When moving heavy parts or machinery, which if the following is most important? -
correct answer Establishing good communication with coworkers
What size must a dumbwaiter cab enclosure be to transport people? -correct answer
Dumbwaiter s may only transport materials, not people
While working on a moving walk, where are barriers required? -correct answer At the
points embarkation and disembarkation
At which point on the lifeline should your lanyard be attached? -correct answer
Above your shoulder
A construction crew arrives to work on Monday morning and finds the overhead
machine room floor is being poured. What precautions shoot be taken? -correct
answer Avoid working in the hoistway
,100 elevator final exam (Latest
Update) Questions and Verified Answers
100% Correct {Grade A}
What are 2 types of mechanical drawings used in elevator installations? -correct
answer Layout drawing, detail drawing
You are installing a V-belt drive pulley on a 40 horse motor for a hydraulic pump unit.
What type of acre is needed to lock down the pulley to motor shaft? -correct answer
Hexagonal socket with cup head screws
You must order enough wire to complete installation of a duplex. Where would you
find the information that would determine how much wire is needed? -correct answer
Electrical layout
In the metric system, how is the measurement of volume identified? -correct answer
Liter
Refer to print 1. Which view shows the pit depth? -correct answer A. Elevation view
You are installing rails in a new building. Which drawing will you reference? -correct
answer Rail installation detail drawing
What part of the job folder would contain information regarding elevator speed,
capacity, and loading class? -correct answer Abstract
, 100 elevator final exam (Latest
Update) Questions and Verified Answers
100% Correct {Grade A}
When replacing typical rollers on guides, what is the appropriate tool and fastener to
be used? -correct answer Snap ring pliers/ snap rings
What method should an elevator constructor use to check the well hole depth? -
correct answer Drop a weight led line to the bottom and measure the line
What is the simplest locking device used to prevent loosening due to vibrations? -
correct answer Jam type nuts
When installing pipe, what type of threads would you use to create a proper seal? -
correct answer Pipe threads
What information is typically provided in a job folder? -correct answer Contract
speed, car platform thickness, machine groove type
In a mechanical drawing, which symbol would refer to diameter? -correct answer Zero
with a line through it
Where would an elevator constructor find information pertaining to platform
dimensions? -correct answer Final layout
Which of the following terms describes and architectural drawing that shows three
sides at once? -correct answer Three-dimensional drawing