TEST BANK FOR PMI (PMP) EXAM 6TH EDITION
PMBOK||NEWEST EXAM!!! (COMPLETE SOLUTION)
FULLY COVERED NEWEST VERSION||VERIFIED
EXAM!!!
Which Knowledge Area involves identifying the people,
groups, or organizations that may be impacted by or
impact a project?
A. Project Risk Management
B. Project Human Resource Management
C. Project Scope Management
D. Project Stakeholder Management - Answer-D
Which input to Collect Requirements is used to identify
stakeholders who can provide information on
requirements?
A. Stakeholder register
B. Scope management plan
C. Stakeholder management plan
D. Project charter - Answer-A
,2|Page
In which Knowledge Area is the project charter
developed?
A. Project Cost Management
B. Project Scope Management
C. Project Time Management
D. Project Integration Management - Answer-D
The ability to influence cost is greatest during which
stages of the project?
A. Early
B. Middle
C. Late
D. Completion - Answer-A
Which process involves developing an approximation of
the monetary resources needed to complete project
activities?
A. Estimate Costs
,3|Page
B. Control Costs
C. Determine Budget
D. Plan Cost Management - Answer-A
Which tool or technique is used in the Develop Project
Management Plan process?
A. Pareto diagram
B. Performance reporting
C. SWOT analysis
D. Expert judgment - Answer-D
The organization's perceived balance between risk taking
and risk avoidance is reflected in the risk:
A. Responses
B. Appetite
C. Tolerance
D. Attitude - Answer-A
An output of the Manage Stakeholder Engagement
process is:
, 4|Page
A. change requests
B. enterprise environmental factors
C. the stakeholder management plan
D. the change log - Answer-A
Which process numerically analyzes the effect of identified
risks on overall project objectives?
A. Plan Risk Management
B. Plan Risk Responses
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis - Answer-C
Which Collect Requirements output links the product
requirements to the deliverable that satisfy them?
A. Requirements documentation
B. Requirements traceability matrix
C. Project management plan updates
D. Project documents updates - Answer-B