OECP TEST NEW ACTUAL EXAM QUESTIONS AND ANSWERS LATEST UPDATE 2026/2027 | GRADED A+. The minimum distance to power lines 0-350kv : 350kv to 1,000kv A. 10' : 15' B. 20' : 50' C. 40' : 80' D. 25' : 55' -correct answer-B. 20' : 50' A shift inspection must be completed when? A. At the end of the shift B. Before or during that shift C. Before the start of the next day D. At the end of the safety meeting -correct answer-B. Before or during that shift Who must inspect a machine that has been idle for 3 months or more? 2 | Page A. Qualified person B. Competent person C. Missing person D. Any person -correct answer-A. Qualified person If a crane is not set up level and the operator swings a load from the high side to the low side, the load radius will: A. Decrease B. Stay the same C. Increase two feet for every one degree out of level D. Increase -correct answer-D. increase How is a signalman identified? A. By following signal of the person who knows what is going on and who seems to take control of the operation B. By the person that is giving signals and who is wearing the white clean gloves. C. By a pre lift meeting with crane operator and rigging crew D. Designated a signalman and tell the crew who he is. -correct answer-C. By a pre lift meeting with crane operator and rigging crew 3 | Page Quickly lowering and stopping the load can: A. Reduce break heat up by reducing friction. B. Increase the loading on the crane and cause it to fail structurally or to become unstable also known as shock landing. C. Save break wear and bearing by reducing drum RPM D. Prolong life of hydraulic pump by reducing its use. -correct answer-B. Increase the loading on the crane and cause it to fail structurally or to become unstable also known as shock landing. Boom extensions and jibs are: A. Used to increase radius and are rated on stability B. Not to be used to hoist personnel C. Used to increase boom length D. To be used for single line hoisting only -correct answer-C. Used to increase boom length In order to control the drift of the load, the operator must: A. Keep boom tip over the load 4 | Page B. Allow load to touch the ground

Show more Read less
Institution
OECP
Course
OECP











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
OECP
Course
OECP

Document information

Uploaded on
December 12, 2025
Number of pages
41
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • oecp

Content preview

1 | Page


OECP TEST NEW ACTUAL EXAM QUESTIONS
AND ANSWERS LATEST UPDATE 2026/2027 |
GRADED A+.




The minimum distance to power lines 0-350kv : 350kv to 1,000kv


A. 10' : 15'
B. 20' : 50'
C. 40' : 80'
D. 25' : 55' -correct answer-B. 20' : 50'




A shift inspection must be completed when?


A. At the end of the shift
B. Before or during that shift
C. Before the start of the next day
D. At the end of the safety meeting -correct answer-B. Before or during that shift




Who must inspect a machine that has been idle for 3 months or more?

,2 | Page


A. Qualified person
B. Competent person
C. Missing person
D. Any person -correct answer-A. Qualified person




If a crane is not set up level and the operator swings a load from the high side to
the low side, the load radius will:


A. Decrease
B. Stay the same
C. Increase two feet for every one degree out of level
D. Increase -correct answer-D. increase




How is a signalman identified?


A. By following signal of the person who knows what is going on and who seems
to take control of the operation
B. By the person that is giving signals and who is wearing the white clean gloves.
C. By a pre lift meeting with crane operator and rigging crew
D. Designated a signalman and tell the crew who he is. -correct answer-C. By a pre
lift meeting with crane operator and rigging crew

,3 | Page




Quickly lowering and stopping the load can:


A. Reduce break heat up by reducing friction.
B. Increase the loading on the crane and cause it to fail structurally or to become
unstable also known as shock landing.
C. Save break wear and bearing by reducing drum RPM
D. Prolong life of hydraulic pump by reducing its use. -correct answer-B. Increase
the loading on the crane and cause it to fail structurally or to become unstable
also known as shock landing.




Boom extensions and jibs are:


A. Used to increase radius and are rated on stability
B. Not to be used to hoist personnel
C. Used to increase boom length
D. To be used for single line hoisting only -correct answer-C. Used to increase
boom length




In order to control the drift of the load, the operator must:


A. Keep boom tip over the load

, 4 | Page


B. Allow load to touch the ground
C. Add extra tag lines
D. Determine wind direction -correct answer-A. Keep the boom tip over the load.


A category II operational aid that has malfunctioned must be repaired within
_____ days.


A. 7
B. 14
C. 28
D. 30 -correct answer-D. 30


When using a crane to pick and carry a load you must:


A. Keep the speed as low as possible
B. Avoid Sudden stops and starts
C. Use tag lines if possible to control load
D. All of the above -correct answer-D. All of the above




To restrict access to a crane's swing radius the operator must:


A. Post a signal person
B. Barricade the area around the crane

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
ExcelAcademia2026 Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
2061
Member since
4 year
Number of followers
1648
Documents
7474
Last sold
1 day ago
EXCEL ACADEMIA TUTORS

At Excel Academia Tutoring, You will get solutions to all subjects in both assignments and major exams. Contact me for assistance. Good luck! Well-researched education materials for you. Expert in Nursing, Mathematics, Psychology, Biology etc. My Work has the Latest & Updated Exam Solutions, Study Guides and Notes (100% Verified Solutions that Guarantee Success)

3.7

337 reviews

5
139
4
74
3
62
2
19
1
43

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions