⫸ True or False? If you have Create module generating one-at-a-time
customer arrivals, then it is not possible to use a different Create
module with 4-at-a-time customer arrivals. Answer: False
⫸ True or False? Fake customers can be used to schedule machine
breakdowns, keep track of which time period the simulation is
currently in, and carry out other duties not associated with actual
customers. Answer: True
⫸ Which module/spreadsheet is NOT in the Advanced Process panel?
Answer: Process Model
- The process model is in the Basic Process panel.
Advanced Process Panel
-Seize module
-Delay module
-Release module
-Expression spreadsheets
-Failure spreadsheets
, ⫸ Why are things like Seize, Delay, Release in multiple templates?
Answer: The process module does not allow us to use Seize, Delay,
Release with sufficient generality.
⫸ True or False? You can schedule failures to occur after a random
number of customers have used a resource or after a random amount
of time has passed. Answer: True
⫸ True or False? You are only allowed to schedule one type of failure
for a particular resource. Answer: False
⫸ Which block is NOT in the Blocks template? Answer: Process
Block
- No such thing, but the Process module is in the Basic Process panel
Blocks template:
- Seize block
- Delay block
- Release block
- Alter block
- Queue block
⫸ True or False? The Queue block can connect up to the Seize
module from the Advanced Process template. Answer: False
⫸ Which kinds of sets are allowed? Answer: - Resource set