CQM-C EXAM QUESTIONS AND ANSWERS GRADED
A+||NEWEST EXAM!!!
The purpose of Construction Quality Management is to: -
Answer-Achieve the quality established by properly
developed requirements through the combined
responsibility, but seperate efforts of contractpr smd
government personnel.
Construction Quality Management is the performance of
tasks, which ensure that construction is performed. -
Answer-According to plans and specifications, on time,
within a defined budget and a safe work environment.
Partnering relationships are based upon: - Answer-
Building trust and dedication to common goals
It is the responsibility of Quality Assurance Personnel to: -
Answer-Periodically verify that the contractors system of
control is working effectively.
An effective contractor quality control program will: -
Answer-Be an incentive for work to be done correctly the
, 2|Page
first time resulting in earlier completion, reduced field
overhead costs, and greater profits.
The success or failure of all contractors is based upon: -
Answer-The ability to control costs, finance work, estimate
jobs, schedule the work, and maintain effective quality
control.
Quality Assurance Personnel have the responsibility to: -
Answer-Require contractors to maintain the quality
specified in the plans and specifications.
Inspection is: - Answer-The process by which ongoing and
completed work is examined
During the punch-out inspection of a project: - Answer-
Quality Assurance Personnel must assure that the
contractor prepares a punch-list and makes corrections.
If there is a disagreement whether the contractors work
complies with the contract: - Answer-The government
makes the final determination