OSCM Exam 2 Questions with Correct Answers Latest Update 2025/2026 Project - Answers A series of related jobs usually directed toward some major output and requiring a significant period of time to perform. Project Management - Answers Planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project. Pure project - Answers A structure for organizing a project where a selfcontained team works full time on the project. Functional project - Answers In this structure, team members are assigned from the functional units of the organization. The team members remain a part of their functional units and typically are not dedicated to the project. matrix project - Answers A structure that blends the functional and pure project structures. Each project uses people from different functional areas. A dedicated project manager decides what tasks need to be performed and when, but the functional managers control which people to use. Project milestone - Answers A specific event in a project. Work breakdown structure (WBS) - Answers The hierarchy of project tasks, subtasks, and work packages. Activities - Answers Pieces of work within a project that consume time. The completion of all the activities of a project marks the end of the project. Gantt chart - Answers Shows in a graphic manner the amount of time involved and the sequence in which activities can be performed. Often referred to as a bar chart. Earned Value Management (EVM) - Answers Technique that combines measures of scope, schedule, and cost for evaluating project progress. Critical path - Answers The sequence(s) of activities in a project that form the longest chain in terms of their time to complete. This path contains zero slack time. It is possible for there to be multiple critical paths in a project. Techniques used to find the critical path are called CPM, or critical path method, techniques. immediate predecessor - Answers Activities that need to be completed immediately before another activity. slack time - Answers The time that an activity can be delayed without delaying the entire project; the difference between the late and early start times of an activity. Early start schedule - Answers A project schedule that lists all activities by their early start times. Late start schedule - Answers A project schedule that lists all activities by their late start times.

Show more Read less
Institution
OSCM
Course
OSCM








Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
OSCM
Course
OSCM

Document information

Uploaded on
December 5, 2025
Number of pages
4
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

OSCM Exam 2 Questions with Correct Answers Latest Update 2025/2026

Project - Answers A series of related jobs usually directed toward some major output and
requiring a significant period of time to perform.

Project Management - Answers Planning, directing, and controlling resources (people,
equipment, material) to meet the technical, cost, and time constraints of a project.

Pure project - Answers A structure for organizing a project where a selfcontained team works
full time on the project.

Functional project - Answers In this structure, team members are assigned from the functional
units of the organization. The team members remain a part of their functional units and typically
are not dedicated to the project.

matrix project - Answers A structure that blends the functional and pure project structures. Each
project uses people from different functional areas. A dedicated project manager decides what
tasks need to be performed and when, but the functional managers control which people to use.

Project milestone - Answers A specific event in a project.

Work breakdown structure (WBS) - Answers The hierarchy of project tasks, subtasks, and work
packages.

Activities - Answers Pieces of work within a project that consume time. The completion of all
the activities of a project marks the end of the project.

Gantt chart - Answers Shows in a graphic manner the amount of time involved and the
sequence in which activities can be performed. Often referred to as a bar chart.

Earned Value Management (EVM) - Answers Technique that combines measures of scope,
schedule, and cost for evaluating project progress.

Critical path - Answers The sequence(s) of activities in a project that form the longest chain in
terms of their time to complete. This path contains zero slack time. It is possible for there to be
multiple critical paths in a project. Techniques used to find the critical path are called CPM, or
critical path method, techniques.

immediate predecessor - Answers Activities that need to be completed immediately before
another activity.

slack time - Answers The time that an activity can be delayed without delaying the entire project;
the difference between the late and early start times of an activity.

Early start schedule - Answers A project schedule that lists all activities by their early start times.

Late start schedule - Answers A project schedule that lists all activities by their late start times.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
joshuawesonga22 Liberty University
View profile
Follow You need to be logged in order to follow users or courses
Sold
20
Member since
7 months
Number of followers
1
Documents
9195
Last sold
5 days ago
Tutor Wes

Hi there! I'm Tutor Wes, a dedicated tutor with a passion for sharing knowledge and helping others succeed academically. All my notes are carefully organized, detailed, and easy to understand. Whether you're preparing for exams, catching up on lectures, or looking for clear summaries, you'll find useful study materials here. Let’s succeed together!

3.0

1 reviews

5
0
4
0
3
1
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions