MANG 3402 FINAL CH. 3,5,7,8 QUESTIONS

Institution
MANG 3402
Course
MANG 3402










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
MANG 3402
Course
MANG 3402

Document information

Uploaded on
November 19, 2025
Number of pages
21
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

MANG 3402 FINAL CH. 3,5,7,8 QUESTIONS

The project organization may be LESS helpful when
A.
the job is familiar to the existing organization.

B.
work tasks can be defined with a specific goal and deadline.
C.
the project cuts across organizational lines.
D.
the work contains complex interrelated tasks requiring specialized skills. - Answer -A.
the job is familiar to the existing organization.

Which of the following is a direct responsibility of the project manager?
A.
drawing the network diagram
B.
making sure that the people assigned to the project receive the motivation, direction,
and information needed to do their jobs
Your answer is correct.
C.
performing all of the activities in the project
D.
calculating completion probabilities for all tasks in the project - Answer -B.
making sure that the people assigned to the project receive the motivation, direction,
and information needed to do their jobs

Which of these statements is NOT true about project scheduling?
A.
Project scheduling encourages the setting of realistic time and cost estimates for each
activity.
B.
Project scheduling helps make better use of resources by identifying the non-critical
paths through the network.
.
C.
Project scheduling identifies the precedence relationships among activities.
D.
Project scheduling shows the relationship of each activity to ot - Answer -B.
Project scheduling helps make better use of resources by identifying the non-critical
paths through the network.
.

The critical path of a network is the

,A.
shortest time path through the network.
B.
longest time path through the network.

C.
path with the most activities.
D.
path with the fewest activities. - Answer -B.
longest time path through the network.

Dummy activities
A.
are used when two activities have identical starting and ending events.

B.
are found in both AOA and AON networks.
C.
cannot be on the critical path.
D.
have a duration equal to the shortest non-dummy activity in the network. - Answer -A.
are used when two activities have identical starting and ending events.

Which of the following steps is NOT a basic step followed by PERT and CPM?
A.
Define the project.
B.
Draw the network connecting all the activities.
C.
Compute the critical path.
D.
Identify and eliminate non-critical activities - Answer -D.
Identify and eliminate non-critical activities

How is the EF computed?
A.
Min{LS of all immediate following activities}
B.
ES + Activity time

C.
LF −Activity time
D.
Max{EF of all immediate predecessors} - Answer -B.
ES + Activity time

, The latest finish of an activity is
A.
LF−Activity
time.
B.
Min{LS of all immediate following activities}.

C.
ES + Activity time.
D.
Max{EF of all immediate predecessors}. - Answer -B.
Min{LS of all immediate following activities}.

With respect to PERT and CPM, slack
A.
marks the start or completion of a task.
B.
is a task or subproject that must be completed.
C.
is the amount of time a task may be delayed without changing the overall project
completion time.
D.
is the latest time an activity can be started without delaying the entire project. - Answer
-C.
is the amount of time a task may be delayed without changing the overall project
completion time.

Which of the following sets is determined during a backward pass?
A.
LS and EF
B.
LS and LF

C.
LS and ES
D.
ES and EF - Answer -B.
LS and LF

What is the shortest duration required to complete an activity?
A.
optimistic time
B.
pessimistic time
C.
most likely time

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GEEKA YALA UNIVERSITY
View profile
Follow You need to be logged in order to follow users or courses
Sold
2011
Member since
3 year
Number of followers
1447
Documents
48584
Last sold
11 hours ago

3.8

345 reviews

5
172
4
61
3
44
2
16
1
52

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.