CTQP Final Estimates 1 Questions with
Answers (100% Correct Answers)
A major function of the DOT is to carry out the construction and improvement
of transportation facilities so the public is provided with adequate
transportation service.— Answer: True
Multiple choice. For the DOT, the management of Construction projects
involves the following specific responsibilities: A. Planning, Programming and
Design B. Contract Administration C. Contractor Payments D. Contract
Management E. All of the above— Answer: E. All of the above
True or false. Contractors are paid for the work performed through progress
and final estimates.— Answer: True
Multiple choice. Which of the following is NOT officially considered to be a
"Contract Document"? A. Supplemental Agreements and Work Orders B.
Field Records C. Standard Specifications D. Construction Project
Administration Manual (CPAM) E. Answers B & D— Answer: E. Answers B
&D
Multiple choice. Between the scheduled publishing of the Standard
Specifications, what does the Department issue to identify and describe changes
in the Standard Specifications? A. Construction Project Administration Manual
(CPAM) B. Supplemental Specifications C. Work Orders D. Supplemental
Agreements— Answer: B. Supplemental Specifications
Multiple choice. Select the correct sequence of documents in order of
precedence, with the document highest in authority listed first. A. Contract
Plans, Development Specifications, Standard Specifications, Special
Provisions, Technical Special Provisions, Supplemental Specifications,
Standard Plans. B. Standard Plans, Special Provisions, Technical Special
Provisions, Supplemental Specifications, Contract Plans, development
Specifications, Standard Specifications. C. Special Provisions, Technical
, 2
Special Provisions, Contract Plans, Standard Plans, Development
Specifications, Supplemental Specifications, Standard Specifications. D.
Supplemental Specifications, Special Provisions, Contract Plans, Development
Specifications, Sandards Specifications, Technical Special Provisions, Standard
Plans. E. None of the above.— Answer: C. Special Provisions, Technical
Special Provisions, Contract Plans, Standard Plans, Development
Specifications, Supplemental Specifications, Standard Specifications.
True or false. Special provisions are contract documents that may describe a
situation unique to a specific project or modify a requirement set forth in the
Specifications.— Answer: True
Multiple choice. Which of the following documents sets forth the Department's
methods and procedures for preparing and submitting a final estimate? A.
Construction Inspection Mathematics B. Project Engineer Manual C.
Construction Project Administration Manual D. The Review & Administration
Manual— Answer: C. Construction Project Administration Manual
True or False. Progress payments are made to contractors on a monthly basis.
A. True B. False— Answer: True
Multiple Choice. Which of the following is not a site source record? A. Final
Estimates Forms B. Field Book C. Supplemental Agreement D. Final As-Built
Plans— Answer: C. Supplemental Agreement
Multiple choice. When using calculators or computers, you should use the: A.
Rules of rounding described in Construction Math Course B. Full decimal
capabilities of the machine C. Construction Project Administration Manual as
a guide to rounding D. Machine only as a backup to your manual
computations E. None of the above— Answer: B. Full decimal capabilities of
the machine
Field books— Answer: hard bound source documents used primarily for
sketches or renderings of items in the field. However they can also be used to
document field measurements and calculations for establishing pay quantities.