Questions with Correct Answers 2025
The NACE Inspector should perform tests for soluble salts: - CORRECT ANSWER -
When specified
Corrosion generally occurs at which of the following sites: - CORRECT ANSWER -Anode
If inspectors identify issues of non-conformance during an inspection, they should -
CORRECT ANSWER -
inform both the Contractor and the inspector's supervisor so they can take appropriate corr
ective actions
You are the NACE Inspector on a job where ISO ST 3 has been specified. The Contractor no
rmally works to SSPC standards and been referencing SSPC SP 3. Could this have any impact
on the final surface preparation appearance? - CORRECT ANSWER -
No, because there is no real difference in the standards
Safety Data Sheets must be carefully reviewed by: - CORRECT ANSWER -
All personnel involved in the job
You are the NACE Inspector on a job where the Owner's specification requites you to perfor
m a twice daily check of blast pressure at the nozzle. It is now day 30 on the job and all of
your readings have been within compliance. The Contractor complains that these checks ta
king up much time and in view of the compliant results they are unnecessary. Your FIRST pr
eferred course of action is to: - CORRECT ANSWER -
Keep doing the checks and consult the Owner's representative for direction