📌📌- 1 Code to follow when performing an internal inspection on pipe
API 510
570: 5.5.2 -
📌📌- 2 Positive Material Identification (PMI)
API 578
570: 5.12 -
📌📌- 3 Fitness for Service (FFS)
API 579
570: 7.7 -
📌📌- 4 Risked Based Inspection (RBI)
API 580
570: 5.2 -
📌📌- 5 Corrosion Under Insulation (CUI)
API 583
570: 5.8 -
📌📌- 6 Valve Inspection & Testing
API 598
570: 5.13 -
📌📌- 7 Cathodic Protection
API 651
570: 9.6 -
📌📌- 8 Welding on In-Service Equipment containing Flammables
API 2201
570: 8.2.1 -
📌📌- 9 NDE Procedure Guidelines
ASME Sect V
31.3: 343 -
📌📌- 10 Design code for fabrication of piping relief devices
ASME Sect 8
31.3: 322.6.3.a -
📌📌- 11 Welder & Weld Procedure Qualification
ASME Sect 9
31.3: 328.2 -
📌📌
ASNT SNT-TC-1A or CP-189
V: T-120.e - - 12 NDE Personnel Qualification
📌📌- 1 API 570 Scope (Alteration, Inspection, Repair, Rerate)
AIRR
570: 1.1.1 -
📌📌- 2 API 570 AI's Employer (Jurisdiction, User, Insurance company, Contractor)
JUIC
570: 3.1.6 -
, 📌📌
SOPI
570: 7.3 - - 5 Determine Corrosion Rate for New Service or Change in Service (Same or
Similar Service, Owner's Experience, Published Data, or Inspect in 3 months)
📌📌
Physical Change
570: 3.1.3 - - 1 Define - Alteration
📌📌
Restore - Suitable
570: 3.1.88 - - 2 Define - Repair
Cyclic Stress
📌📌- 3 Corrosion - Cause for fatigue crack
570: 3.1.18
574: 7.4.11 -
📌📌- 4 Define - Imperfection that exceeds the acceptance criteria
Defect
570: 3.1.22 -
📌📌- 5 Define - Discontinuity that may or may not exceed the acceptance criteria
Imperfection
570: 3.1.35 -
📌📌
Probability & Consequence
570: 5.2.1 - - 6 Define - RBI's two Primary Factors
📌📌
Process Fluid & Volume
570: 5.2.3 - - 7 RBI - Two Primary Factors of Consequence of Failure
📌📌
Representative
570: 5.15 - - 8 Repairs - # of new flange assemblies to be inspected during repairs and
alterations
📌📌
Consequence of failure
570: 6.3.4.1 - - 9 Insp - Basis of API 570's Piping Classification
📌📌- 10 Corrosion - Method by which process leaks can lead to brittle failure
Auto-refigeration
570: 6.3.4.2.a -
📌📌- 11 NDE - Number of CMLs to obtain thickness readings during inspection
Representative
570: 6.5.1 -
📌📌
CML w/ earliest renewal date
570: 6.5.1 - - 12 NDE - CML that must be measured during a Thickness Inspection
📌📌- 13 PRD's - How relief device intervals are determined
Performance
570: 6.7.3.1 -
📌📌
Low Resistivity
570: 9.5 - - 14 Corrosion - Type of soil that is most corrosive
📌📌
Time, Temp, & Stress
574: 7.4.12 - - 15 Corrosion - Factors that affect the creep rate
-0.010"