A+ VERIFIED 2025 - 2026 UPDATE
"Because of the temporary nature of and the potential benefits that may
be derived from reducing the post-project cost of quality, __________
may choose to invest in product quality improvement, especially in the
areas of prevention and appraisal:
A. Sponsoring organizations.
B. The project management team.
C. The project executive management team.
D. The project quality function deployment (QFD) organization.
" - correct answer- A
\which of the following is a tool and technique used in the perform
qualitative risk analysis? - correct answer- risk categorziation
a change control board (CCB) is - correct answer- A formally
chartered group responsible for reviewing, evaluating, approving,
delaying, or rejecting changes to the project, and for recording and
communicating such decisions.
,a documented economic feasibility study used to establish the validity of
the benefits of a selected component lacking sufficient definition and
that is used as a basis for the authorization fo further project
management activities is which of the following? - correct answer-
buisness case
a significant amount of data is collected and analyzed throughout the
project. All of the following are examples of project data and
information except: - correct answer- work performance analysis
A thorough analysis of the ____________________ will help identify
potential risks to the project. - correct answer- risk identification
checklist based on historical information and knowledge
all legal contractual relationships generally fall into one of the following
broad categories except - correct answer- request for proposal (RFP)
all of the following are characteristics of the project charter except: -
correct answer- formally authorizes the existence of a project
all of the following are data analysis techniques used in project closeout
except - correct answer- regression analysis used to determine
which indiviual project risks or other sources of uncertainty have the
mose potential impact on project outcomes
,all of the following are data analysis techniques used in project closeout
except: - correct answer- regression analysis...
all of the following are EEF's except: - correct answer- economic
conditions
all of the following are inputs to manage project knowledge except: -
correct answer- knowledge management
all of the following are inputs to manage project knowledge except: -
correct answer- knowledge management
all of the following are inputs to the control schedule process, except: -
correct answer-
all of the following are inputs to the estimate activity resource process
except: - correct answer- resource breakdown structure
all of the following are inputs to the estimate activity resources process
except: - correct answer- resource breakdown structure
all of the following are outputs to close project or phase except: -
correct answer- EEF's
, all of the following are outputs to close project or phase except: -
correct answer- EEF's
all of the following are potential information in organizational
knowledge repositories except: - correct answer- tactic knowledge
of previous projects such as project performance data and lessons
learned
list of employees
all of the following are trrue about the project scope mgmt plan except:
- correct answer- it describes how the scope will be defined,
developed, monitored, controlled and validated
all of the following are true about affinity diagrams except: - correct
answer- They are used to identify the key issues and the suitable
alternatives to be prioritized as a set of decisions for implementation
all of the following are true about project phases and the project life
cycle except: - correct answer- cost and staffing levels are generally
steady throughout the project life cycle
all of the following are true about the SOW for a procurement except -
correct answer- it can be ambiguous or incomplete