100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

EICA CRANE CERTIFICATION EXAM SCRIPT 2026 COMPLETE QUESTIONS AND ANSWERS 100% CORRECT

Rating
-
Sold
-
Pages
16
Grade
A+
Uploaded on
12-11-2025
Written in
2025/2026

EICA CRANE CERTIFICATION EXAM SCRIPT 2026 COMPLETE QUESTIONS AND ANSWERS 100% CORRECT

Institution
EICA Crane
Course
EICA Crane










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
EICA Crane
Course
EICA Crane

Document information

Uploaded on
November 12, 2025
Number of pages
16
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

EICA CRANE CERTIFICATION (2025) EXAM
QUESTIONS AND ALL CORRECT ANSWERS 100%
SOLVED AND GUARANTEED SUCCESS!!

Section 1: Safety Procedures & Regulations

1. What is the primary purpose of a pre-operational inspection?
A) To fill out paperwork for management.
B) To identify and correct any potential hazards or defects before use.
C) To practice crane movements.
D) To check the weather forecast.

2. According to OSHA standards, who is qualified to perform maintenance or repair on a
crane's electrical system?
A) Any experienced crane operator.
B) A qualified electrician or technician.
C) The site foreman.
D) The rigger.

3. What must an operator do if a crane's load block shows signs of cracking during inspection?
A) Continue operation but at a reduced capacity.
B) Report the defect and remove the crane from service until repaired.
C) Weld the crack during the next break.
D) Ignore it if the crack is small.

4. The standard hand signal for "STOP" is:
A) Arm extended, palm down, moving side to side.
B) Arm extended, palm open and down, held stationary.
C) A closed fist pumped up and down.
D) Pointing repeatedly at the ground.

5. What is the minimum safe distance a crane should maintain from energized power lines?
A) 5 feet
B) 10 feet
C) It depends on the line's voltage, as specified in OSHA standards.
D) 20 feet, regardless of voltage.

,6. A "DANGER" or "OUT OF ORDER" tag on a crane control means:
A) The operator can remove it if they need to use the crane.
B) Only a supervisor can authorize its removal.
C) The crane must not be operated, and only an authorized person can remove the tag.
D) It is a suggestion for careful operation.

7. The purpose of a load moment indicator (LMI) is to:
A) Weigh the load precisely.
B) Warn the operator when the crane is approaching its rated capacity.
C) Control the crane's hoisting speed.
D) Record the number of lifts made.

8. Before making a lift, the operator must ensure:
A) The load is within the crane's rated capacity for the configuration.
B) The path is clear and the load is properly rigged.
C) All personnel are clear of the load and the load path.
D) All of the above.

9. If a crane loses power while holding a load, the operator should:
A) Jump out of the cab immediately.
B) Engage the emergency stop.
C) Place all controls in the "OFF" or "NEUTRAL" position.
D) Attempt to lower the load using the emergency backup system if trained and it is safe to do
so.

10. A daily inspection of the crane should include checking:
A) Wire rope for signs of damage or wear.
B) Fluid levels (hydraulic oil, coolant).
C) Functional operation of all safety devices and alarms.
D) All of the above.

Section 2: Electrical Systems & Components

11. The main power source for an EICA crane is typically:
A) A diesel generator on the crane.
B) A connection to the facility's electrical grid via a collector system.
C) A bank of batteries.
D) Solar panels.

, 12. What is the function of a slip ring assembly on an overhead crane?
A) To provide a continuous electrical connection to the bridge girder.
B) To allow the transmission of power and signals to the hoist trolley.
C) To act as the main circuit breaker.
D) To ground the crane.

13. A megohmmeter (megger) is used to test:
A) Voltage levels.
B) Current flow.
C) Insulation resistance of motor windings and cables.
D) Continuity of control circuits.

14. An electrical ground on a crane is essential for:
A) Providing a return path for fault current and protecting personnel.
B) Increasing the crane's lifting capacity.
C) Improving wireless signal strength.
D) Powering the control pendant.

15. What is the likely cause if a crane's motor hums but doesn't turn when activated?
A) The motor is overloaded.
B) A single phasing condition or a faulty starter contact.
C) The voltage is too high.
D) The limit switch is activated.

16. Variable Frequency Drives (VFDs) are used on crane hoists to:
A) Provide smooth acceleration and deceleration control.
B) Increase the motor's maximum speed beyond its design.
C) Generate electrical power during lowering.
D) Replace the need for a brake.

17. The emergency stop button, when pressed, should:
A) Only stop the bridge movement.
B) Open the main line contactor, removing power from all crane motions.
C) Only sound an alarm.
D) Lower the load safely to the ground.

18. In a control circuit, a holding contact (seal-in circuit) is used to:
A) Maintain the circuit after the start button is released.
B) Increase the current to the motor.
$11.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
lecStudyNest

Get to know the seller

Seller avatar
lecStudyNest Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
1
Member since
1 month
Number of followers
0
Documents
184
Last sold
4 days ago

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions