WGU C722 Project Management Pre-assessment
Actual Exam – Complete 70 Questions and Correct
Verified Answers/ C722 Pre-assessment Test
A project was authorized as an operational necessity to
repair a design flaw in the date field on a computer
system that constrains the year number to two digits
instead of permitting the year to be indicated with four
digits. During execution of the activity concerned with
identifying the affected software, five relevant software
modules were discovered that had not been included in
the scope baseline. The project team must adjust the
baselines to include the omitted scope.
Which change management phase does this scenario
describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - ...ANSWER...✓✓ a) Preparing
for the change
,2|Page
A general contractor is managing a highway construction
project that will repair a flood-damaged road. The
Department of Transportation offered an incentive fee if
the repairs are completed early. Therefore, the project
manager has established a rewards and recognition
program and has communicated this program to the
project team member. The project's recognition program
will reward project team members who add value by
accelerating the project while maintaining its ability to
deliver the completed scope correctly.
Which change management phase does this scenario
describe?
a) Preparing for the change
b) Managing the change
c) Reinforcing the change
d) Upgrading the change - ...ANSWER...✓✓ c) Reinforcing
the change
A general contractor is managing a construction project
that will add a new conference room to an existing office
building. The project was documented in a fixed-price
contract that specified a completion date. The contract
,3|Page
includes a damages clause imposing a late completion
penalty if the conference room is not ready for use by the
due date. One month into the implementation, the
customer wants to modify the room's lighting equipment.
The requested change will delay the project's critical path
by three months.
Which process should be used to maintain the existing
baseline?
a) Using a change management system to influence
performance
b) Absorbing the change request in the baselines for time
and cost
c) Focusing on the original scope
d) Using the risk management system to process change
requests - ...ANSWER...✓✓ a) Using a change
management system to influence performance
A general contractor from Germany is managing a
construction project in Norway that will add a new
conference room to an existing office building. The project
needs to collect requirements from the client prior to
developing plans to build the new conference room.
, 4|Page
Which two actions would prove useful to plan the
project's quality?
a) Defining traceable and verifiable requirements that can
be validated at project closure
b) Establishing metrics that describe what to measure
and how to measure it
c) Using inventory to protect against defects during
project implementation
d) Changing the work plan to account for the project
experiencing common variation
e) Using slogans and numerical quotas to exhort
resources to work harder - ...ANSWER...✓✓ a & b
a) Defining traceable and verifiable requirements that can
be validated at project closure
b) Establishing metrics that describe what to measure
and how to measure it
What is the name for the closing task where all project
activities are reviewed to determine what went right and
what went wrong?