1 || |P |a |g
|e
OECP TEST 2025 BRAND NEW ACTUAL EXAM
WITH ANSWERS
The minimum distance to power lines 0-350kv : 350kv to 1,000kv
| | | | | | | | | |
A. 10' : 15' | |
B. 20' : 50' | |
C. 40' : 80' | |
D. 25' : 55' -correct answer-B. 20' : 50'
| | | | | | |
A shift inspection must be completed when?
| | | | | |
A. At the end of the shift
| | | | |
B. Before or during that shift
| | | |
C. Before the start of the next day
| | | | | |
D. At the end of the safety meeting -correct answer-B. Before or during that shift
| | | | | | | | | | | | |
Who must inspect a machine that has been idle for 3 months or more?
| | | | | | | | | | | | |
,2 || |P |a |g
|e
A. Qualified person |
B. Competent person |
C. Missing person |
D. Any person -correct answer-A. Qualified person
| | | | |
A category II operational aid that has malfunctioned must be repaired within
| | | | | | | | | | |
days.
A. 7
B. 14
C. 28
D. 30 -correct answer-D. 30
| | |
If a crane is not set up level and the operator swings a load from the high side to
| | | | | | | | | | | | | | | | | |
|the low side, the load radius will:
| | | | | |
A. Decrease
B. Stay the same | |
C. Increase two feet for every one degree out of level
| | | | | | | | |
D. Increase -correct answer-D. increase
| | |
,3 || |P |a |g
|e
How is a signalman identified?
| | | |
A. By following signal of the person who knows what is going on and who seems
| | | | | | | | | | | | | |
to take control of the operation
| | | | | |
B. By the person that is giving signals and who is wearing the white clean gloves.
| | | | | | | | | | | | | |
C. By a pre lift meeting with crane operator and rigging crew
| | | | | | | | | |
D. Designated a signalman and tell the crew who he is. -correct answer-C. By a pre
| | | | | | | | | | | | | |
lift meeting with crane operator and rigging crew
| | | | | | | |
Quickly lowering and stopping the load can:
| | | | | |
A. Reduce break heat up by reducing friction. | | | | | |
B. Increase the loading on the crane and cause it to fail structurally or to become
| | | | | | | | | | | | | |
unstable also known as shock landing.
| | | | | |
C. Save break wear and bearing by reducing drum RPM
| | | | | | | |
D. Prolong life of hydraulic pump by reducing its use. -correct answer-B. Increase
| | | | | | | | | | |
the loading on the crane and cause it to fail structurally or to become unstable
| | | | | | | | | | | | | | |
also known as shock landing.
| | | | |
Boom extensions and jibs are:
| | | |
A. Used to increase radius and are rated on stability
| | | | | | | |
B. Not to be used to hoist personnel
| | | | | |
, 4 || |P |a |g
|e
C. Used to increase boom length
| | | |
D. To be used for single line hoisting only -correct answer-C. Used to increase
| | | | | | | | | | | |
boom length
| |
In order to control the drift of the load, the operator must:
| | | | | | | | | | |
A. Keep boom tip over the load
| | | | |
B. Allow load to touch the ground
| | | | |
C. Add extra tag lines
| | |
D. Determine wind direction -correct answer-A. Keep the boom tip over the load.
| | | | | | | | | | |
When using a crane to pick and carry a load you must:
| | | | | | | | | | |
A. Keep the speed as low as possible
| | | | | |
B. Avoid Sudden stops and starts
| | | |
C. Use tag lines if possible to control load
| | | | | | |
D. All of the above -correct answer-D. All of the above
| | | | | | | | |
To restrict access to a crane's swing radius the operator must:
| | | | | | | | | |
|e
OECP TEST 2025 BRAND NEW ACTUAL EXAM
WITH ANSWERS
The minimum distance to power lines 0-350kv : 350kv to 1,000kv
| | | | | | | | | |
A. 10' : 15' | |
B. 20' : 50' | |
C. 40' : 80' | |
D. 25' : 55' -correct answer-B. 20' : 50'
| | | | | | |
A shift inspection must be completed when?
| | | | | |
A. At the end of the shift
| | | | |
B. Before or during that shift
| | | |
C. Before the start of the next day
| | | | | |
D. At the end of the safety meeting -correct answer-B. Before or during that shift
| | | | | | | | | | | | |
Who must inspect a machine that has been idle for 3 months or more?
| | | | | | | | | | | | |
,2 || |P |a |g
|e
A. Qualified person |
B. Competent person |
C. Missing person |
D. Any person -correct answer-A. Qualified person
| | | | |
A category II operational aid that has malfunctioned must be repaired within
| | | | | | | | | | |
days.
A. 7
B. 14
C. 28
D. 30 -correct answer-D. 30
| | |
If a crane is not set up level and the operator swings a load from the high side to
| | | | | | | | | | | | | | | | | |
|the low side, the load radius will:
| | | | | |
A. Decrease
B. Stay the same | |
C. Increase two feet for every one degree out of level
| | | | | | | | |
D. Increase -correct answer-D. increase
| | |
,3 || |P |a |g
|e
How is a signalman identified?
| | | |
A. By following signal of the person who knows what is going on and who seems
| | | | | | | | | | | | | |
to take control of the operation
| | | | | |
B. By the person that is giving signals and who is wearing the white clean gloves.
| | | | | | | | | | | | | |
C. By a pre lift meeting with crane operator and rigging crew
| | | | | | | | | |
D. Designated a signalman and tell the crew who he is. -correct answer-C. By a pre
| | | | | | | | | | | | | |
lift meeting with crane operator and rigging crew
| | | | | | | |
Quickly lowering and stopping the load can:
| | | | | |
A. Reduce break heat up by reducing friction. | | | | | |
B. Increase the loading on the crane and cause it to fail structurally or to become
| | | | | | | | | | | | | |
unstable also known as shock landing.
| | | | | |
C. Save break wear and bearing by reducing drum RPM
| | | | | | | |
D. Prolong life of hydraulic pump by reducing its use. -correct answer-B. Increase
| | | | | | | | | | |
the loading on the crane and cause it to fail structurally or to become unstable
| | | | | | | | | | | | | | |
also known as shock landing.
| | | | |
Boom extensions and jibs are:
| | | |
A. Used to increase radius and are rated on stability
| | | | | | | |
B. Not to be used to hoist personnel
| | | | | |
, 4 || |P |a |g
|e
C. Used to increase boom length
| | | |
D. To be used for single line hoisting only -correct answer-C. Used to increase
| | | | | | | | | | | |
boom length
| |
In order to control the drift of the load, the operator must:
| | | | | | | | | | |
A. Keep boom tip over the load
| | | | |
B. Allow load to touch the ground
| | | | |
C. Add extra tag lines
| | |
D. Determine wind direction -correct answer-A. Keep the boom tip over the load.
| | | | | | | | | | |
When using a crane to pick and carry a load you must:
| | | | | | | | | | |
A. Keep the speed as low as possible
| | | | | |
B. Avoid Sudden stops and starts
| | | |
C. Use tag lines if possible to control load
| | | | | | |
D. All of the above -correct answer-D. All of the above
| | | | | | | | |
To restrict access to a crane's swing radius the operator must:
| | | | | | | | | |