Which one of the Following is not a Project Delivery System?
At-Risk CM
Design-Bid-Build
Professional CM (Agency CM)
Multiple Prime Contracting ✔Correct Answer-Professional CM (Agency CM)
In lump-sum contracts, the Owner assumes the risk of the cost
True or False ✔Correct Answer-False
Typically, The design reviewer has the ultimate responsibility and authority to make executive
decisions to matters affecting time and money in a construction project
True or False ✔Correct Answer-False
In The Design-Build Project delivery system, the Owner has separate contracts with the Designer and
the Contractor
True or False ✔Correct Answer-False
The Resident Project Representative should stop the work of the Contractor when the work is not
performed according to the drawings and specifications
True or False ✔Correct Answer-False
Which of the Following should not be performed by the Resident Project Representative?
1. Ensuring that all work activities of contractor are inspected daily
2. Providing instructions directly to subcontractors
3. Approving the work that meets the contract requirements
4. Following up the work that requires corrections ✔Correct Answer-2. Providing instructions
directly to subcontractors
Which of the following is not true for the construction diary?
1. Every working day should be reported even if no work is reported
2. It should be in ink if it is handwritten
3. There should be page numbers on every page
4. Entries should be made on a weekly basis ✔Correct Answer-4. Entries should be made on a
weekly basis
Ambiguous language in a contract is interpreted against the party who selected the language or
supplied the contract
True or False ✔Correct Answer-True
, According to Spearin Doctrine, when the contractor exactly follows the detail specifications and
drawings, she/he will not be responsible for unsatisfactory results in the end product
True or False ✔Correct Answer-True
Shop Drawings Can be used as change orders
True or False ✔Correct Answer-False
Which one of the following is not an element of the contract as we discussed in class?
1. Acceptance
2. Offer
3. Promise
4. Consideration ✔Correct Answer-3. Promise
Which of the following is not a condition where a contract will not be enforced by courts?
1.Duress
2. Unconscionability
3. Illegality
4. Seniority ✔Correct Answer-4. Seniority
Fill in the blank in the following statement: Some contracts must in writing under the ________ as
adopted by each state 1. Resource Conservation and Recovery Act
2. Statue of Frauds
3. Davis Bacon Act
4. Statue of Limitations ✔Correct Answer-2. Statue of Frauds
RFI is the document that is transmitted to the GC from the Designer to get clarifications with respect
to design drawings and specifications
True or False ✔Correct Answer-False
The Resident Project Representative should not supervise, direct, or control the contractors means
and methods of performing work
True or False ✔Correct Answer-True
In Fast-Track projects with multiple contractors, the services of a professional construction
management firm (Agency CM) are essential
True or False ✔Correct Answer-True
The design-build process may face some legal barriers when tried to be implemented in the public
sector
True or False ✔Correct Answer-True
On a multiple-prime project, the owner is responsible for coordinating the various trade contractors
with whom it has contracted