Twentieth Century Public contracting laws in North America have historically mandated
professional design services be purchased separated from the selection of contractors solely on
the basis of lowest responsible bid. T or F? - CORRECT ANSWER - True
Most Public Procurement statutes require the selection of design services be purchased on the
basis of lowest responsible bid? T/F? - CORRECT ANSWER - False
There are always at least three parties involved in every project delivery process; the Owner,
Architect and Contractor. T/F? - CORRECT ANSWER - True
It is recommended to get a contractor on board early during the business and planning stage of a
DB project to have the best opportunity to achieve all objectives. T/F - CORRECT
ANSWER - True
The primary goal in choosing a delivery method is to ensure that it will meet the Owner's project
objectives while at the same time allowing the project to be completed on time and within
budget? T/F - CORRECT ANSWER - True
CM @ Risk project delivery is faster than Design-Bid-Build, but can be slower than Design-
Build. T/F - CORRECT ANSWER - True
Fast tracking a project and phased construction is possible using the CM @ Risk project delivery
method. t/f? - CORRECT ANSWER - true
The owner can pre-determine how a project's construction team will interact with him or her and
with each other through the selection of the delivery system. T/F? - CORRECT
ANSWER - True