100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

APM PFQ EXAM QUESTIONS WITH 100- COMPLETE SOLUTIONS

Rating
-
Sold
-
Pages
52
Grade
A+
Uploaded on
25-10-2025
Written in
2025/2026

APM PFQ EXAM QUESTIONS WITH 100- COMPLETE SOLUTIONS

Institution
APM PFQ
Course
APM PFQ











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
APM PFQ
Course
APM PFQ

Document information

Uploaded on
October 25, 2025
Number of pages
52
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

APM PFQ EXAM QUESTIONS WITH
100% COMPLETE SOLUTIONS 2025-2026
Which of the following is not a stage in an issue resolution process?
a. Share the issue with stakeholders.
b. Track the issue to closure. c. Escalate to the sponsor.
d. Apply change control. - ANSWER-A

Which of the following are challenges for a project manager developing and leading a
project team?
1) Issues and incompatibility amongst team members
2) Getting the right skills and attributes amongst team members
3) Co-location of team members in the same geographic area
4) Lack of accountability of team members
a. 1, 2 & 3
b. 1, 2 & 4
c. 1, 3 & 4
d. 2, 3 & 4 - ANSWER-C

Which of the following is an activity in a typical change control process?
a. Recommendation.
b. Justification.
c. Planning.
d. Continuous improvement - ANSWER-A

The purpose of quality assurance is to:
a. provide confidence the project will satisfy the relevant quality standards.
b. determine a set of procedures and standards for project management.
c. inspect, measure and test deliverables and processes.
d. define the scope and specifics of a project's deliverables - ANSWER-A

A project manager might use a PESTLE analysis in order to:
a. mitigate all possible risks to the project.
b. identify and mitigate factors that may affect the project.
c. control technological change during the project.
d. consider team social roles in early stages of the project - ANSWER-B

Which of the following are phases in an iterative project life cycle? 1) Concept 2)
Feasibility 3) Deployment 4) Development
a. 3 and 4 only
b. 1, 2 and 3
c. 1 and 2 only
d. 2, 3 and 4 - ANSWER-D

,Which of the following is the responsibility of a project manager?
a. Ensuring a project is aligned to the organisation's strategy.
b. Focusing on project benefits and aligning priorities.
c. Achieving the project's success criteria.
d. Improving process, tools and techniques used in a project - ANSWER-C

To develop and establish a proper communication plan within a project, the project
manager needs to consider which type of analysis?
a. Budget.
b. Stakeholder.
c. Resource.
d. Schedule - ANSWER-B

Which of the following is a responsibility of the project sponsor?
a. Creating a project cost breakdown structure.
b. Authoring the project management plan.
c. Creating a project work breakdown structure.
d. Owning the project business case. - ANSWER-D

Portfolio management includes prioritising:
a. projects and/or programmes that contribute directly to the organisation's strategic
objectives.
b. projects with exceptionally high returns on investment.
c. projects and programmes over business as usual.
d. projects which maximise change over those which maximise investment - ANSWER-
A

Which of the following actions would not help a team leader influence the performance
of their team?
a. Creating an exclusive environment.
b. Providing clear roles and responsibilities.
c. Promoting openness and honesty.
d. Developing a trusting relationship. - ANSWER-A

One difference between a project and business as usual is:
a. projects achieve specified benefits but business as usual has only vague benefits.
b. projects drive change whereas business as usual continues existing activities.
c. projects have tightly controlled budgets whereas business as usual does not.
d. projects have unclear deadlines but business as usual has multiple milestones -
ANSWER-B

The purpose of project progress reporting is to:
a. ensure a simpler critical path.
b. enable the tracking of project deliverables.
c. ensure stakeholder acceptance of project deliverables.
d. provide an increased total float. - ANSWER-B

,Which of the following is the purpose of an estimating funnel?
a. Keeping resource usage to a minimum to help reduce costs.
b. Supporting the production of comparative estimates.
c. Identifying where costs can be minimised when preparing a budget.
d. Representing increasing levels of estimating accuracy achieved through the life cycle
- ANSWER-D

One advantage of virtual communications is:
a. that nonverbal signals can have an impact on discussions.
b. it's easy to detect signs of conflict within the project team.
c. access to a wider resource pool for the project.
d. that the project team will always be co-located. - ANSWER-C

Which technique could be used by a project manager when resources are limited?
a. Resource aggregation.
b. Resource estimation.
c. Resource levelling.
d. Resource expansion - ANSWER-C

The main aim of quality management is to:
a. prepare a high-quality management plan.
b. ensure that deliverables meet appropriate standards.
c. validate the use of consistent standards.
d. determine whether to accept change requests. - ANSWER-B

Which of the following is a purpose of issue management?
a. To stop issues occurring within the project.
b. To address and resolve the issues that occur.
c. To address and resolve uncertainty.
d. To reschedule activities to reduce costs - ANSWER-B

Product breakdown structures illustrate the required scope of work by a hierarchical
structure itemising the:
a. components of each product.
b. budget of each product.
c. benefits of each product.
d. risks of each product. - ANSWER-A

The definition of benefits management includes which key activities?
a. Planning, analysis and integration of project benefits.
b. Justification, validation and acceptance of project benefits.
c. Identification, tracking and realisation of project benefits.
d. Realisation, acceptance and integration of project benefits - ANSWER-C

Which of the following statements about scheduling is false?

, a. Defines the sequence of activities.
b. Considers work calendars and time contingency.
c. Provides a baseline for safety considerations.
d. Quantifies the required resources. - ANSWER-C

Which of the following defines the term 'deployment baseline'?
a. The starting point for creating a resource histogram.
b. The basis for creating an organisational breakdown structure.
c. The starting point for the monitoring of project risks.
d. The basis for progress monitoring. - ANSWER-D

Which of the following is an activity in a typical configuration management process?
a. Evaluation.
b. Identification.
c. Registration.
d. Justification. - ANSWER-B

Stakeholder analysis supports effective stakeholder engagement by:
a. identifying stakeholders with high levels of power and interest.
b. ensuring stakeholder acceptance of project deliverables.
c. justifying the preferred project option to stakeholders.
d. providing information to all stakeholders. - ANSWER-A

Which of the following is a project?
a. Introducing a new information technology system.
b. Operating a national rail network.
c. Organising ongoing catering in the armed forces.
d. Managing day-to-day security for senior politicians - ANSWER-A

One purpose of a typical project business case is to:
a. carry out earned value analysis.
b. allocate resources to the project.
c. analyse cost-benefit of the project.
d. plan project work packages - ANSWER-C

One disadvantage of physical communication is:
a. its significant environmental impact when compared to other forms of communication.
b. that no audit trail is available for review at a later date by project team members.
c. it is reliant on technology being available to all relevant members of the project.
d. that your body language may not reflect what you're saying when passing on
information - ANSWER-A

One of the benefits of developing communication plans in projects is that this ensures:
a. the power and influence of stakeholders is understood.
b. that all communication is delivered face to face.
c. your message is understood.
$11.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
LeeErickson

Get to know the seller

Seller avatar
LeeErickson Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
2
Member since
7 months
Number of followers
0
Documents
1282
Last sold
1 month ago

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions