The realization of a typical building project, as described in this text, may be divided
into:
a. two phases.
b. three phases.
c. four phases.
d. five phases.
e. six phases. - n
Ans✔
d. five phases.
Qs
Establishing the project's economic feasibility and its overall budget is part of the
design phase of the project.
a. True
b. False - n
Ans✔
b. False
Qs
The term MEPF stands for:
a. mechanical, electrical, piping, and foundations.
b. mechanical, electrical, plumbing, and foundations.
c. mechanical, electrical, plumbing, and fire.
d. mechanical, electrical, piping, and fire. - n
Ans✔
c. mechanical, electrical, plumbing, and fire.
, Qs
The program for a building project is usually provided by the:
a. owner.
b. general contractor.
c. building official of the city.
d. architect.
e. any one of these, depending on the type of building. - n
Ans✔
a. owner.
Qs
In a typical building project, the coordination of the building's design is done by
the:
a. owner.
b. general contractor.
c. building official of the city
d. architect.
e. any one of these, depending on the type of building. - n
Ans✔
d. architect.
Qs
The construction drawings of a building project are prepared during the:
a. SD stage of the project.
b. DD stage of the project.
c. CD stage of the project.
d. preconstruction phase of the project.
e. construction phase of the project. - n
Ans✔