A full lot of super pave asphalt is what size?
1,000 tons
1,000 to 2000 tons
2000 to 4000 tons
1 days production - 🧠ANSWER ✔✔2000 to 4000 tons
Which is not typically used as an asphalt binder in fdot mix designs?
PG 52-28
PG 58-22
PG 62-22
, PG 76-22(PMA)
PG 82-22 (PMA) - 🧠ANSWER ✔✔PG 62-22
Who cuts the density cores used for verification testing?
The verification technician
The contractor
The independent verification testing technician
None of the above - 🧠ANSWER ✔✔The contractor
A full lot is composed of 5 sublots and 4 cores per lot T/F - 🧠ANSWER
✔✔False
What is the most important for consistent compaction of asphalt mix?
The mix is hotter in temperature
The mix is colder in temperature
The mix is uniform in temperature
Temperature of the mix does not affect compaction - 🧠ANSWER ✔✔The
mix is uniform in temperature
Referring to general stationing guidelines, R1 would be ____ than R2