I Questions with Correct and
Verified Answers
"Compaction factor - Correct Answer The difference between the volume of the hole to be
filled and the volume of fill material"
"Bank measure - Correct Answer Bank measure amounts are obtained by using the
dimensions of the holes excavated or filled with no adjustment made to the quantities
obtained for swell or compaction of materials. These factors will be accounted for when the
takeoff items are priced."
"Two-Stage process of calculating number of masonry units - Correct Answer 1. The area of
masonry is measured.
2. A standard factor is applied to determine the number of masonry units required for area
measured."
Conceptual Estimate - Correct Answer Produced from merely the notion the owner has of
what he or she would want to construct. Answers the question, "can i build the project for
this amount?""
"Preliminary Estimates - Correct Answer Can assist designers by providing cost information
about alternative design details."
"3 Factors for how an estimator prepares estimate - Correct Answer 1. The type of project to
be built
2. The delivery system used to move from the developer's project idea to a finished structure
3. The nature of the contract(s) used in the delivery system"
"Detailed Estimate Stages - Correct Answer 1. Quantity Takeoff
2. Recap Quantities
3. Pricing the Recap
4. Pricing Subcontractor's Work
5. Pricing General Expenses
6. Summary and Bid"
, "Query List - Correct Answer An estimator's list of all questions that arise during the quantity
takeoff process, that will be compiled and the questions will be directed towards the
designer."
"Addenda - Correct Answer Significant details from query list that will be incorporated into
written documents that are distributed to all bidders."
"Five Categories of units used in estimating - Correct Answer 1. Number (counting number of
items)
2. Length (in linear ft.)
3. Area (sq. ft.)
4. Volume (cu. yd.)
5. Weight (lbs. or Ton)"
"Deductions in takeoff - Correct Answer Written in red or enclosed in brackets "< >" and noted
as deductions"
"Estimating Assemblies - Correct Answer An assembly is a component of the work that can
be considered separately from the other parts of the work."
"Swell factor - Correct Answer The difference between the volume of the hole and the
volume of the material once it has been dug out"
"Measuring formwork - Correct Answer Measured in square feet of contact area, and is
classified in the same categories in the same categories as those listed for concrete.
Bulkheads, pilasters and edge forms shall be measured separately."
"Openings in formwork estimate - Correct Answer No deduction is made from the total area
of the forms if the size of the opening is less than 100 square feet."
"Estimating Slab Finishes - Correct Answer Measured in square feet (slab finishes) of plan
area, and vertical finishes are measured in sq. ft. of exposed surface of concrete. Finishes are
classified in terms of what is being finished (slabs, walls, etc.) then separated by type of
finish (wood float, sack rubbed, etc.). Also, if floor hardeners are required they are measured
separately by lb/100ft.^2"
"Measuring Screeds and Curing Slabs - Correct Answer Screeds measured in square feet as
plan area of the slab. Measure curing slabs and vapor barrier slabs in plan area, but due to
laps an additional 10% is added to the area."