Chapter 5 pt.2 Questions and
Answers
"What is the relationship between organizational culture and estimating?
A. There is no relationship
B. Cultural norms affect the accuracy of estimates
C. Culture determines whether estimates are made
D. Estimating alters cultural norms
E. Estimating and culture are independent - Correct Answer b"
"A good starting point for developing time and cost estimates is
A. Past experience.
B. Work packages.
C. Task analysis.
D. Time and motion studies.
E. Work breakdown structure. - Correct Answer a"
"Which of the following is NOT one of the factors that need to be considered to improve
quality of estimates for project times and costs?
A. Planning horizon
B. People
C. Padding estimates
D. Profit
E. Project structure - Correct Answer d"
The process of forecasting or approximating the time and cost of completing project
deliverables is called
A. Budgeting.
, B. Predicting.
C. Estimating.
D. Planning.
E. Guesstimating. - Correct Answer c"
"In practice, estimating processes are frequently classified as
A. Top down/bottom up.
B. Rough/polished.
C. Precise/order of magnitude.
D. Draft/final.
E. Broad/Specific. - Correct Answer a"
"Ed is looking over the actual results of projects and comparing them to what was estimated.
He notices that the projects that took six months or longer to complete were noticeably more
off the estimates. Which of the following factors is he recognizing?
A. Padding estimates
B. Project duration
C. Project structure
D. People
E. Organization culture - Correct Answer b"
"Janet is forecasting how much money her department needs to support a new project. She
estimates that two people and $25,000 in expenses will cover her needs. Because
management typically insists on reducing forecasts by 20 percent, she increases her
estimates to allow for that reduction. Which of the following factors is illustrated in this
situation?
A. Padding estimates
B. Planning horizon
C. Project structure
D. People
E. Organization culture - Correct Answer a"