Question 1. Which North Carolina General Statute grants local governments the authority to enforce the
State Building Code?
A) GS 143-138
B) GS 160D-1110
C) GS 150B-23
D) GS 90-210
Answer: B
Explanation: GS 160D-1110 empowers local governments to enforce the State Building Code in North
Carolina.
Question 2. What is the main purpose of the North Carolina State Building Code?
A) Generate revenue for municipalities
B) Protect public health, safety, and general welfare
C) Facilitate architectural innovation
D) Promote economic development
Answer: B
Explanation: The primary purpose is to safeguard public health, safety, and welfare through regulation
of building construction.
Question 3. Who issues certificates of occupancy in North Carolina?
A) The general contractor
B) The property owner
C) The code enforcement official
D) The architect
Answer: C
Explanation: Only the code enforcement official is authorized to issue certificates of occupancy upon
compliance with codes.
Question 4. What is the minimum fire-resistance rating required for a fire wall in a Type I construction
building?
A) 1 hour
B) 2 hours
C) 3 hours
D) 4 hours
Answer: C
Explanation: Type I construction requires fire walls to have a minimum 3-hour fire-resistance rating.
Question 5. Which occupancy classification applies to a building used for office purposes?
A) Assembly (Group A)
B) Business (Group B)
C) Mercantile (Group M)
D) Institutional (Group I)
Answer: B
Explanation: Office buildings are classified as Business (Group B) occupancies.
Question 6. When is a permit required under the NC Building Code?
A) For all work, regardless of scope
, Grove Large Telescopic Swing Cab Crane Exam
B) Only for new buildings
C) For construction, alteration, repair, movement, demolition, or change of occupancy
D) Only for electrical work
Answer: C
Explanation: Permits are required for all these activities to ensure code compliance.
Question 7. Which code section governs the appeals process for code enforcement decisions in NC?
A) Administrative Code, Section 101
B) North Carolina General Statute 160D-1127
C) Building Code, Chapter 2
D) Fire Code, Section 403
Answer: B
Explanation: GS 160D-1127 outlines the appeals process for code enforcement decisions.
Question 8. Who determines the occupancy classification of a building?
A) The owner
B) The architect
C) The code enforcement official
D) The fire marshal
Answer: C
Explanation: The code enforcement official is responsible for determining the correct occupancy
classification.
Question 9. Which document must be provided before a building can be occupied?
A) Statement of Special Inspections
B) Certificate of Occupancy
C) Zoning permit
D) Architectural drawings
Answer: B
Explanation: A Certificate of Occupancy is required before any building can be legally occupied.
Question 10. What is the maximum allowable height for a Type IIIB building, Group R-2, without
sprinklers?
A) 40 feet
B) 55 feet
C) 65 feet
D) 75 feet
Answer: B
Explanation: For Group R-2, Type IIIB, the maximum allowable height without sprinklers is 55 feet.
Question 11. Which type of construction requires all structural elements to be noncombustible?
A) Type I and II
B) Type III
C) Type IV
D) Type V
Answer: A
Explanation: Type I and II require noncombustible structural elements.
, Grove Large Telescopic Swing Cab Crane Exam
Question 12. How often must building inspectors in North Carolina complete continuing education?
A) Every year
B) Every two years
C) Every three years
D) Every five years
Answer: A
Explanation: North Carolina building inspectors must complete continuing education annually.
Question 13. What information must be included in a permit application?
A) Owner name, estimated cost, scope of work, and plans
B) Contractor’s lunch menu
C) Utility bills
D) Previous inspection reports
Answer: A
Explanation: These details are necessary for permit review and code compliance.
Question 14. Which of the following best defines a change of occupancy?
A) Repair of interior finishes
B) Alteration of a roof
C) Change in the purpose or level of activity
D) Installation of new mechanical equipment
Answer: C
Explanation: A change of occupancy involves changing the building’s use or level of activity.
Question 15. What is the minimum depth for frost protection of footings in North Carolina unless
protected by other means?
A) 6 inches
B) 12 inches
C) 18 inches
D) 24 inches
Answer: D
Explanation: The minimum depth for frost protection is 24 inches below grade.
Question 16. What is the Building Code Council responsible for?
A) Issuing permits
B) Adopting and amending the NC State Building Code
C) Conducting inspections
D) Reviewing architectural plans
Answer: B
Explanation: The Council adopts and amends the NC State Building Code.
Question 17. Who is responsible for scheduling special inspections as required by the Building Code?
A) The owner
B) The contractor
C) The design professional in responsible charge
D) The building inspector
, Grove Large Telescopic Swing Cab Crane Exam
Answer: C
Explanation: The design professional in responsible charge arranges special inspections.
Question 18. What is the purpose of a Certificate of Compliance?
A) Authorizes temporary equipment use
B) Certifies completion of a specified scope of work
C) Confirms payment of fees
D) Grants a zoning variance
Answer: B
Explanation: It certifies that a specific scope of work complies with code requirements.
Question 19. Which occupancy group includes hospitals and nursing homes?
A) Group A
B) Group B
C) Group I
D) Group R
Answer: C
Explanation: Hospitals and nursing homes are classified as Institutional (Group I).
Question 20. What triggers the requirement for a plan review by the code enforcement official?
A) Any new structure, addition, or major alteration
B) Only residential structures
C) Only buildings over 10,000 square feet
D) Only government buildings
Answer: A
Explanation: Plan review is required for all new structures, additions, or major alterations.
Question 21. Which code section establishes the minimum requirements for means of egress?
A) Chapter 5
B) Chapter 6
C) Chapter 10
D) Chapter 13
Answer: C
Explanation: Chapter 10 addresses minimum means of egress requirements.
Question 22. What is the minimum fire-resistance rating for a corridor serving an occupant load greater
than 30 in a non-sprinklered Group B building?
A) 0 hours
B) 0.5 hours
C) 1 hour
D) 2 hours
Answer: C
Explanation: A 1-hour fire-resistance rating is required in this scenario.
Question 23. What must be posted on the job site for the duration of construction?
A) Construction schedule
B) Permit card
Question 1. Which North Carolina General Statute grants local governments the authority to enforce the
State Building Code?
A) GS 143-138
B) GS 160D-1110
C) GS 150B-23
D) GS 90-210
Answer: B
Explanation: GS 160D-1110 empowers local governments to enforce the State Building Code in North
Carolina.
Question 2. What is the main purpose of the North Carolina State Building Code?
A) Generate revenue for municipalities
B) Protect public health, safety, and general welfare
C) Facilitate architectural innovation
D) Promote economic development
Answer: B
Explanation: The primary purpose is to safeguard public health, safety, and welfare through regulation
of building construction.
Question 3. Who issues certificates of occupancy in North Carolina?
A) The general contractor
B) The property owner
C) The code enforcement official
D) The architect
Answer: C
Explanation: Only the code enforcement official is authorized to issue certificates of occupancy upon
compliance with codes.
Question 4. What is the minimum fire-resistance rating required for a fire wall in a Type I construction
building?
A) 1 hour
B) 2 hours
C) 3 hours
D) 4 hours
Answer: C
Explanation: Type I construction requires fire walls to have a minimum 3-hour fire-resistance rating.
Question 5. Which occupancy classification applies to a building used for office purposes?
A) Assembly (Group A)
B) Business (Group B)
C) Mercantile (Group M)
D) Institutional (Group I)
Answer: B
Explanation: Office buildings are classified as Business (Group B) occupancies.
Question 6. When is a permit required under the NC Building Code?
A) For all work, regardless of scope
, Grove Large Telescopic Swing Cab Crane Exam
B) Only for new buildings
C) For construction, alteration, repair, movement, demolition, or change of occupancy
D) Only for electrical work
Answer: C
Explanation: Permits are required for all these activities to ensure code compliance.
Question 7. Which code section governs the appeals process for code enforcement decisions in NC?
A) Administrative Code, Section 101
B) North Carolina General Statute 160D-1127
C) Building Code, Chapter 2
D) Fire Code, Section 403
Answer: B
Explanation: GS 160D-1127 outlines the appeals process for code enforcement decisions.
Question 8. Who determines the occupancy classification of a building?
A) The owner
B) The architect
C) The code enforcement official
D) The fire marshal
Answer: C
Explanation: The code enforcement official is responsible for determining the correct occupancy
classification.
Question 9. Which document must be provided before a building can be occupied?
A) Statement of Special Inspections
B) Certificate of Occupancy
C) Zoning permit
D) Architectural drawings
Answer: B
Explanation: A Certificate of Occupancy is required before any building can be legally occupied.
Question 10. What is the maximum allowable height for a Type IIIB building, Group R-2, without
sprinklers?
A) 40 feet
B) 55 feet
C) 65 feet
D) 75 feet
Answer: B
Explanation: For Group R-2, Type IIIB, the maximum allowable height without sprinklers is 55 feet.
Question 11. Which type of construction requires all structural elements to be noncombustible?
A) Type I and II
B) Type III
C) Type IV
D) Type V
Answer: A
Explanation: Type I and II require noncombustible structural elements.
, Grove Large Telescopic Swing Cab Crane Exam
Question 12. How often must building inspectors in North Carolina complete continuing education?
A) Every year
B) Every two years
C) Every three years
D) Every five years
Answer: A
Explanation: North Carolina building inspectors must complete continuing education annually.
Question 13. What information must be included in a permit application?
A) Owner name, estimated cost, scope of work, and plans
B) Contractor’s lunch menu
C) Utility bills
D) Previous inspection reports
Answer: A
Explanation: These details are necessary for permit review and code compliance.
Question 14. Which of the following best defines a change of occupancy?
A) Repair of interior finishes
B) Alteration of a roof
C) Change in the purpose or level of activity
D) Installation of new mechanical equipment
Answer: C
Explanation: A change of occupancy involves changing the building’s use or level of activity.
Question 15. What is the minimum depth for frost protection of footings in North Carolina unless
protected by other means?
A) 6 inches
B) 12 inches
C) 18 inches
D) 24 inches
Answer: D
Explanation: The minimum depth for frost protection is 24 inches below grade.
Question 16. What is the Building Code Council responsible for?
A) Issuing permits
B) Adopting and amending the NC State Building Code
C) Conducting inspections
D) Reviewing architectural plans
Answer: B
Explanation: The Council adopts and amends the NC State Building Code.
Question 17. Who is responsible for scheduling special inspections as required by the Building Code?
A) The owner
B) The contractor
C) The design professional in responsible charge
D) The building inspector
, Grove Large Telescopic Swing Cab Crane Exam
Answer: C
Explanation: The design professional in responsible charge arranges special inspections.
Question 18. What is the purpose of a Certificate of Compliance?
A) Authorizes temporary equipment use
B) Certifies completion of a specified scope of work
C) Confirms payment of fees
D) Grants a zoning variance
Answer: B
Explanation: It certifies that a specific scope of work complies with code requirements.
Question 19. Which occupancy group includes hospitals and nursing homes?
A) Group A
B) Group B
C) Group I
D) Group R
Answer: C
Explanation: Hospitals and nursing homes are classified as Institutional (Group I).
Question 20. What triggers the requirement for a plan review by the code enforcement official?
A) Any new structure, addition, or major alteration
B) Only residential structures
C) Only buildings over 10,000 square feet
D) Only government buildings
Answer: A
Explanation: Plan review is required for all new structures, additions, or major alterations.
Question 21. Which code section establishes the minimum requirements for means of egress?
A) Chapter 5
B) Chapter 6
C) Chapter 10
D) Chapter 13
Answer: C
Explanation: Chapter 10 addresses minimum means of egress requirements.
Question 22. What is the minimum fire-resistance rating for a corridor serving an occupant load greater
than 30 in a non-sprinklered Group B building?
A) 0 hours
B) 0.5 hours
C) 1 hour
D) 2 hours
Answer: C
Explanation: A 1-hour fire-resistance rating is required in this scenario.
Question 23. What must be posted on the job site for the duration of construction?
A) Construction schedule
B) Permit card