CompTIA Project+ Cert-Master Practice Test 2024- 2025

Institution
CompTIA Project+
Course
CompTIA Project+











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CompTIA Project+
Course
CompTIA Project+

Document information

Uploaded on
September 15, 2025
Number of pages
43
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • comptia project

Content preview

CompTIA Project+ Cert-Master Practice Test 2024-
2025
1. A project manager is working on a U.S. government Need-to-know informa-
contract and provides details of sensitive information tion access
that is not available to the remainder of the team.
What type of information is the manager reviewing? Clearance requirements
(Select all that apply.) There's two!

2. A project manager is working on a project in which Trade secret
the project findings provide an advantage over the
competition but do not have approval from the patent
office. What would these project findings be?

3. A local grocery market starts a new delivery service for Operational training
customers using the parent company's new mobile schedules
ordering application. The staff picks items from the
shelves, purchases items using a stored debit or credit
card, packages the items, and delivers them to the
correct address. The store partners with several other
software applications to make the service a unique
and pleasant experience for everyone, such as maps
and driving directions for drivers. The parent com-
pany needs to know the local store's needs for the
project to go live and asks for a formal preliminary
procurement plan. What should the local store NOT
include in the preliminary procurement plan?

4. Which exploratory document do sellers use when Request for bid
deliverables are commodities with precise specifica-
tions, and the price will be the primary determining
factor?

5. A vendor has failed to fulfill its obligations regarding Enforce vendor rules of
a contract. It has put the project at risk of failing to engagement.



, CompTIA Project+ Cert-Master Practice Test 2024-
2025
complete. What can help resolve this situation without
choosing the nuclear litigation option?

6. On a kitchen remodeling project, the scope and key A cost baseline includes
deliverables, the project schedule, duration, dead- cost estimates and con-
lines, costs, and estimates were drawn up in a pre- tingency reserves, while a
liminary scope statement. The scope statement was budget totals cost esti-
given stakeholder approval and the project began. mates, contingency, and
Unfortunately, fuel costs have risen sharply in a short management reserves.
period, and all other costs and expenses increased
across the board. Negotiating pricing on some ma-
terials will also push back some milestones and per-
haps the completion date of the project. Due to these
changes, a project cost baseline was drawn up rather
than a project budget. What is the difference between
a project cost baseline and a project budget?

7. A team receives an email notifying the department New management
that the CEO has just stepped down immediately af-
ter providing the annual work priority guidelines. The
new CEO will be determining new priorities over the
next quarter. What has cascading impacts on the or-
ganization that can cause risk due to the variance in
priorities of work?

8. A storage team wants to keep file sizes from taking up Email
too much storage. Which of the following is the least
effective at reducing the number of files that are the
same?

9. In preparing for a project, two members made con- Compromise
flicting statements regarding the project's timeline.
One stated the timeline is extremely short, while the


, CompTIA Project+ Cert-Master Practice Test 2024-
2025
other noted the timeline is more than enough time. As
the project manager, what kind of conflict resolution
strategy would resolve this conflict by coming to a
middle ground decision?

10. A company wants to buy some multi-function copiers Lease
for their printer upgrade project. They want the ability
to return the equipment at the end of the contract.
Which type of procurement method fulfills this need?

11. A project engineer creates a hybrid project that will SaaS
incorporate never before used information technolo-
gy to support critical functions and reporting. What
is a complete software stack, including the infrastruc-
ture, environments, and the actual product that an
end-user would use?

12. By the end of the planning phase, a project's team Scope description, exclu-
will know much more about the scope and require- sions, and assumptions
ments and can write a detailed scope statement. Dur-
ing the planning phase, there were too many un-
knowns, and there have been many changes during a
project's life cycle. Since the preliminary and detailed
scope statements can use the same format, several
elements would need to be added to the scope state-
ment to make it more accurate. What elements would
be found on a preliminary scope statement without
needing to be added to a detailed scope statement?

13. When performing issue management activities, what Root cause analysis
helps users understand and solve the real problems in
a project instead of repeatedly fixing surface issues?



, CompTIA Project+ Cert-Master Practice Test 2024-
2025
14. A company sends out emails quarterly to employees Reinforce adoption over
on how to use the ticketing system. What does this time.
refresher help accomplish?

15. At a meeting for a finished project, the facilitator The company reduced
praised the project manager (PM) for a "job well high-probability risks and
done." They spoke about how the company stretched is making more money.
its time, resources, and funds to complete the project
on time. There were many boasting executives and
happy stakeholders, and the community seemed sat-
isfied with the manufacturing process since it employs
half the town. All they had to do now was push the
product. Which of the following is NOT a measure of
this project's success?

16. A software development manager wants to keep a Defect log
record of issues that arise during the coding process.
Which of the following will best help the manager with
this?

17. A technician initiates a new project and obtains infor- Enterprise resource plan-
mation on how the team can acquire, manage, and ning
consume resources throughout the project. What can
the technician reference to obtain additional contexts
on these concepts?

18. A project manager has the task of completing a pro- Clearance requirements
ject for the U.S. government. The team members must
submit a background check as part of the assignment
process. What security concept best mandates this
type of background check?

19. Monitor performance.
$13.99
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
Schopenhauer

Get to know the seller

Seller avatar
Schopenhauer Johns Hopkins University
View profile
Follow You need to be logged in order to follow users or courses
Sold
3
Member since
4 months
Number of followers
0
Documents
1258
Last sold
1 month ago
Excellence's Lair ༄

We offer a collection of real exams, study guides and test banks, that ranged from a variety of courses from different schools and university. #

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions