How many forms of identification are required when taking the NERC System
Operator Certification exam?
A) 4
B) 9
C) 1
D) 2
2
The NERC came into existence as a result of the Electric Power Reliability Act of
what year?
A) 1958
B) 2005
C) 1967
D) 1997
1967
,How many certification credentials does NERC have examinations for?
A) 2
B) 4
C) 6
D) 3
4
Match the acronym with the appropriate organization.
FERC North American Electric Reliability Corp
NERC Florida Reliability Coordinating Council
FRCC Reliability First
RF Federal Energy Regulatory Commission
1. FERC Federal Energy Regulatory Commission
2. NERC North American Electric Reliability Corporation
3. FRCC Florida Reliability Coordinating Council
,4. RF Reliability First
True/False
Balancing Authorities are responsible to ensure that transmission facilities are
operated within the limits that are established by the Transmission Owners.
False
The first power pool in the industry was created in 1927 and was known as which
of the following?
Pennsylvania-New Jersey Interconnection
How many Interconnections are there in North America?
A) 4
B) 6
C) 2
D) 8
A) 4
, True/False
All four Interconnections operate at ____ Hz, but are not in synchronization with
each other.
A) 59Hz/False
B) 62Hz/True
C) 60HZ/True
D) 60.02Hz/False
C) 60Hz
How many High-Voltage Direct Current transmission lines are there in operation
between the Western and ERCOT Interconnections?
A) 2
B) 0
C) 5
D) 3
B) 0
True/False
According to the NERC Functional Model, there is no difference between the
function and the entity.