PJM Test UPDATED ACTUAL Exam Questions and CORRECT Answers Which of the following balancing control modes is used by PJM under normal operations? - CORRECT ANSWER -Tie-Line Bias Which of the following influences does PJM consider when performing their system load forecast? - CORRECT ANSWER -Weather Conditions & Day of the Week All of the following are limits that must be submitted to PJM for generating units EXCEPT: 1. Eco Min 2. Eco Max 3. Emergency Max 4. Dynamic Instability - CORRECT ANSWER -Dynamic Instabilit

Show more Read less
Institution
PJM Generation
Course
PJM Generation











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PJM Generation
Course
PJM Generation

Document information

Uploaded on
July 26, 2025
Number of pages
36
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

PJM Test UPDATED ACTUAL Exam
Questions and CORRECT Answers
Which of the following balancing control modes is used by PJM under normal operations? -
CORRECT ANSWER -Tie-Line Bias


Which of the following influences does PJM consider when performing their system load
forecast? - CORRECT ANSWER -Weather Conditions & Day of the Week


All of the following are limits that must be submitted to PJM for generating units EXCEPT:


1. Eco Min
2. Eco Max
3. Emergency Max

4. Dynamic Instability - CORRECT ANSWER -Dynamic Instability


If PJM experienced an event that caused the loss of a 1,000 MW generator, which of the
following would most likely provide the quickest impact to improve the undegenerating Area
Control Area (ACE)?


1. Remedial Action Reserve
2. Synch Reserve
3. Non-Synch Reserve

4. Secondary Reserve - CORRECT ANSWER -Synch Reserve


Your system has experienced an event that caused the frequency to drop below 60.00 Hz, what
would be the most likely event that occurred? - CORRECT ANSWER -A generator on
your system tripped offline

,How does the PJM dispatcher inform the Members of the PJM regulation Requirements? -
CORRECT ANSWER -All-Call


In order for your generator to quality to supply regulation in the PJM Regulation market, it must
be able to respond and attain its desired output within how many minutes? - CORRECT
ANSWER -5 minutes


Based on a generator capability curve, in order to maximize the MVAR output of the generator,
it may be necessary to: - CORRECT ANSWER -decrease the MW output of the unit


PJM maintains a regulation quality standard which states that a generator may be certified to
provide regulation only after it achieves three consecutive regulation test scores of at least -
CORRECT ANSWER -75%


Which of the following would NOT be a cause for a sudden deviation in the balancing area
ACE?


1. incorrect interchange number
2. loss of a tie-line RTU
3. loss of internal load

4. loss of adjacent control area generation - CORRECT ANSWER -loss of adjacent control
area generation


The primary purpose for the balancing area to have Regulation is to correct for: - CORRECT
ANSWER -small deviations in load


It is necessary for Generation Owner dispatchers to notify PJM of unplanned unit outages: -
CORRECT ANSWER -as soon as practicable


PJM should be made aware of any fuel shortage that a generator may experience.

,This information assists in analyzing the resources and reliably operating the system. A
heightened awareness is expected during: - CORRECT ANSWER -extreme hot or cold
conditions


Generators are required to obtain PJM approval prior to removing a generating unit from service.


The only exception is for: - CORRECT ANSWER -injury to personnel will be prevented


Prior to removing a self-scheduled generator from service, the PJM member must first -
CORRECT ANSWER -give PJM the option to takeover the unit for the market


When PJM experiences problems with their primary digital control signal, it sometimes becomes
necessary for companies with the capability, to switch to the back-up signal.


This backup signal is known as: - CORRECT ANSWER -Analog control


When PJM sends cost signals to generators, to provide direction for increasing or decreasing the
facility output, this signal that is sent is known as: - CORRECT ANSWER -Dispatch Rate


Under normal operating conditions, what is the limit that will provide the lowest output level of a
generating unit? - CORRECT ANSWER -Eco Min


When PJM send out a cost signal to generators to adjust their output, the generating personnel
adjust the output of the unit base on the unit's - CORRECT ANSWER -price or cost curve
incremental


Which eSuite tool is used to maintain individual generator regulation data that is submitted by
PJM members? - CORRECT ANSWER -eMarket


PJM's ACE configuration is such, that when the ACE is positive (+), it indicates - CORRECT
ANSWER -too much generation

, If a generator is self-scheduled, what is the minimum notification time required in order for the
MW output to be adjusted? - CORRECT ANSWER -20 minutes prior to the change


When corrections are made for the time error and the system scheduled frequency must be
changed to implement the correction, how much is the frequency scheduled adjusted by? -
CORRECT ANSWER -+ /- 0.02 Hz


When PJM runs their Regulation test, how long do the tests normally run? - CORRECT
ANSWER -40 minutes


Your system has a 300 MW steam unit, but due to oil deliveries, the on-site fuel supply is
diminishing.


What is the hourly threshold for reporting to PJM that the unit cannot operate at its maximum
capacity due to the fuel limitation? - CORRECT ANSWER -72 hours


What is the regulation requirement for the PJM balancing area during on-peak hours? -
CORRECT ANSWER -1.0% of the forecasted peak load


What is the time requirement that a generator that wishes to self-schedule itself must provide to
PJM? - CORRECT ANSWER -20 minutes



The PJM Peak Period Maintenance season occurs: - CORRECT ANSWER -Between the
24th & 36th Wednesdays of the year


Maintenance outage extensions may be granted provided that the request for an extension is
made - CORRECT ANSWER -Prior to the end of the outage


What is the maximum time limit for the maintenance outages that occur during the PJM Peak
Period Maintenance season? - CORRECT ANSWER -9 days

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
MGRADES Stanford University
View profile
Follow You need to be logged in order to follow users or courses
Sold
1053
Member since
1 year
Number of followers
100
Documents
68976
Last sold
1 hour ago
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3.8

166 reviews

5
72
4
30
3
42
2
8
1
14

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions