RCDD 12th Edition Chapter 20 Exam Questions and Answers Fully Solved Mills, factories nuclear power plants, government properties = - Answers Require additional training and certification by a local saftey representative Careful attention on the operation of areal butket trucks = - Answers Especially in winter Underground facilities are cables which are placed in = - Answers Subsurfaces conduits using maintenance holes MH's, hand holes HH's, and pull boxes The advantages of underground conduit are that they = - Answers - Preserve the aesthetic appearance of the premises - Are adaptable for future facility placement or removal - Are economical over a long life - Provide the security of additional physical cable protection - Minimize the need for possible subsequent repairs to the Reader Easements from individual property owners are = - Answers Required before any excavation on private property begins Four levels of service diversity = - Answers - Count, among different binder groups - Sheath or cable, among different sheaths or cables - Route, along entirely different cable paths to a building - Backbone, among different intrabuilding backbone cables The ITS designer should consider installing dual services entrances, two 100 percent diverse routes as emergency for back up for buildings that provide continuous services including = - Answers - Hospitals - Airports - Police and fire stations - Military installations - Radio and television stations - Data centers and telephone central offices If you have 588ft of OSP cable between buildings, what's the length of the cable needed ? - Answers 588 + 49 + 49 BICSI recommends a minimum of four [4 trade size] conduits = - Answers With at least one spare 4 trade size conduit that should be considered for each telecommunications service entrance point, in addition with three trade size conduits should be considered Where optical fiber cables will be used the ITS designer should consider placing inner-ducts inside each = - Answers 4 trade size conduit designated for this purpose to ensure physical cable protection Smaller pathway in conduit = - Answers Inner-duct and 1 inch to 2 inch When a building is not on the property line, the building owner should provide - Answers Two or more conduits from a point inside the buildings to the property line or easement Terminate underground conduit at the designated property line or easement with a minimum cover of = - Answers 24 inches In cold climates, minimum burial depth may be greater based on the posted = - Answers 50 year freeze period if applicable The ITS designer should design conduits entering from = - Answers - Below grade point to extend 4 inches above finished floor - Ceiling height to terminate 4 inches below th

Show more Read less
Institution
RCDD
Course
RCDD









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
RCDD
Course
RCDD

Document information

Uploaded on
July 19, 2025
Number of pages
6
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

RCDD 12th Edition Chapter 20 Exam Questions and Answers Fully Solved



Mills, factories nuclear power plants, government properties = - Answers Require additional training and
certification by a local saftey representative

Careful attention on the operation of areal butket trucks = - Answers Especially in winter

Underground facilities are cables which are placed in = - Answers Subsurfaces conduits using
maintenance holes MH's, hand holes HH's, and pull boxes

The advantages of underground conduit are that they = - Answers - Preserve the aesthetic appearance
of the premises

- Are adaptable for future facility placement or removal

- Are economical over a long life

- Provide the security of additional physical cable protection

- Minimize the need for possible subsequent repairs to the Reader

Easements from individual property owners are = - Answers Required before any excavation on private
property begins

Four levels of service diversity = - Answers - Count, among different binder groups

- Sheath or cable, among different sheaths or cables

- Route, along entirely different cable paths to a building

- Backbone, among different intrabuilding backbone cables

The ITS designer should consider installing dual services entrances, two 100 percent diverse routes as
emergency for back up for buildings that provide continuous services including = - Answers - Hospitals

- Airports

- Police and fire stations

- Military installations

- Radio and television stations

- Data centers and telephone central offices

If you have 588ft of OSP cable between buildings, what's the length of the cable needed ? - Answers 588
+ 49 + 49

, BICSI recommends a minimum of four [4 trade size] conduits = - Answers With at least one spare 4 trade
size conduit that should be considered for each telecommunications service entrance point, in addition
with three trade size conduits should be considered

Where optical fiber cables will be used the ITS designer should consider placing inner-ducts inside each =
- Answers 4 trade size conduit designated for this purpose to ensure physical cable protection

Smaller pathway in conduit = - Answers Inner-duct and 1 inch to 2 inch

When a building is not on the property line, the building owner should provide - Answers Two or more
conduits from a point inside the buildings to the property line or easement

Terminate underground conduit at the designated property line or easement with a minimum cover of =
- Answers 24 inches

In cold climates, minimum burial depth may be greater based on the posted = - Answers 50 year freeze
period if applicable

The ITS designer should design conduits entering from = - Answers - Below grade point to extend 4
inches above finished floor

- Ceiling height to terminate 4 inches below the finished ceiling

The penetration is specified for entrance facilities = - Answers As opposed to 1 inch to 3 inch penetration
specified for intra-building conduit

When filling a trench, the earth should be = - Answers Tamped properly to avoid sunken trench
appearance later

B.I.C.S.I recommends that any trench 5ft or more MUST = - Answers - Be shored up to prevent cave in

- Have a minimum clearance 2 ft from the edge of the excavated dirt pile to the nearest edge of the
trench

Limited aerial entrances to small buildings requiring = - Answers - One hundred cable pairs or less for SP
connection

- No other telecommunications entrances

When aerial entrances are used, the span from the last pole to the building must not exceed = - Answers
100 ft, use slack span construction

A vertical conduit may either = - Answers - Terminate in a protector box mounted to the exterior wall

- Enter the building through the roof

To ensure proper support do not extend the mast more than = - Answers 4 inches above the roof line

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorJosh Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
337
Member since
1 year
Number of followers
16
Documents
28501
Last sold
3 hours ago
Tutor Joshua

Here You will find all Documents and Package Deals Offered By Tutor Joshua.

3.6

53 reviews

5
18
4
14
3
12
2
0
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions