If Contractor QC results are not utilized in the acceptance decision, a Dispute Resolution system is not required. (T/F) - CORRECT ANSWER-True All Agency Central laboratories are required under federal regulations to be accredited through the AASHTO Accreditation Program. (T/F) - CORRECT ANSWER-True Personnel Qualification/Certification Programs should include requirements for recertification at 2 to 5 year intervals. (T/F) - CORRECT ANSWER-True Each Agency Construction QA Program must meet requirements of 23 CFR 637B and is required to be approved by the FHWA. (T/F) - CORRECT ANSWER-True Asphalt binder exists in both naturally occurring and manufactured forms. (T/F) - CORRECT ANSWER-True An asphalt binder blended with water in a colloid mill is called an Emulsion. (T/F) - CORRECT ANSWER-True Another appropriate term for asphalt binder is tar. (T/F) - CORRECT ANSWER-False Viscosity: A fluid's ability to flow. (T/F) - CORRECT ANSWER-False (Fluid's resistance to flow) Quality Assurance definition - CORRECT ANSWER-All those planned/systematic actions necessary to provide confidence that a product/facility will perform satisfactorily. A QA Program serves as a skeleton/overall framework necessary for construction QA implementation. (T/F) - CORRECT ANSWER-True Joint development/review of QA specifications should include agency and industry personnel who are directly responsible for construction. (T/F) - CORRECT ANSWERTrue The same six core elements required for Design-Bid-Build construction QA programs are also required for Design-Build. (T/F) - CORRECT ANSWER-True

Show more Read less
Institution
NETTCP Paving Inspector
Course
NETTCP Paving Inspector









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
NETTCP Paving Inspector
Course
NETTCP Paving Inspector

Document information

Uploaded on
July 9, 2025
Number of pages
11
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Content preview

NETTCP Paving Inspector
If Contractor QC results are not utilized in the acceptance decision, a Dispute
Resolution system is not required. (T/F) - CORRECT ANSWER-True

All Agency Central laboratories are required under federal regulations to be accredited
through the AASHTO Accreditation Program. (T/F) - CORRECT ANSWER-True

Personnel Qualification/Certification Programs should include requirements for re-
certification at 2 to 5 year intervals. (T/F) - CORRECT ANSWER-True

Each Agency Construction QA Program must meet requirements of 23 CFR 637B and
is required to be approved by the FHWA. (T/F) - CORRECT ANSWER-True

Asphalt binder exists in both naturally occurring and manufactured forms. (T/F) -
CORRECT ANSWER-True

An asphalt binder blended with water in a colloid mill is called an Emulsion. (T/F) -
CORRECT ANSWER-True

Another appropriate term for asphalt binder is tar. (T/F) - CORRECT ANSWER-False

Viscosity: A fluid's ability to flow. (T/F) - CORRECT ANSWER-False (Fluid's resistance
to flow)


Quality Assurance definition - CORRECT ANSWER-All those planned/systematic
actions necessary to provide confidence that a product/facility will perform satisfactorily.

A QA Program serves as a skeleton/overall framework necessary for construction QA
implementation. (T/F) - CORRECT ANSWER-True

Joint development/review of QA specifications should include agency and industry
personnel who are directly responsible for construction. (T/F) - CORRECT ANSWER-
True

The same six core elements required for Design-Bid-Build construction QA programs
are also required for Design-Build. (T/F) - CORRECT ANSWER-True

QC activities include only sampling/testing. (T/F) - CORRECT ANSWER-False

, QC Plans: project specific documents whose function is to address specific production
facility and field placement processes for individual categories of work on a construction
project. (T/F) - CORRECT ANSWER-True

Acceptance is the responsibility of the transportation agency. (T/F) - CORRECT
ANSWER-True

Engineering Limits: the absolute threshold values for individual test results. (T/F) -
CORRECT ANSWER-True

QA Specifications typically utilize Quality Measures. (T/F) - CORRECT ANSWER-True

Since the objective of the IA comparison is to identify discrepancies or variability in
testing procedures or equipment, IA testing is performed on split samples. (T/F) -
CORRECT ANSWER-True


When exposed to air over an extended period of time, asphalt binder tends to stiffen
and become less flexible. (T/F) - CORRECT ANSWER-True

A PG Binder with a grade of 64-28 would be used in a warmer climate than a PG Binder
of 70-28. (T/F) - CORRECT ANSWER-False

A PG 64-28 may or may not be modified. (T/F) - CORRECT ANSWER-True

The binder supplier should always be consulted for recommendations on the optimum
mixing/compaction temperatures for modified binders for the plant. (T/F) - CORRECT
ANSWER-True

Using the AASHTO M320 criteria: very heavy, slow moving, or standing traffic May
require a grade increase for the high temperature criteria. (T/F) - CORRECT ANSWER-
True

A binder with a rating of 64E-22 means the performance of the binder is Extended on
the high-end. (T/F) - CORRECT ANSWER-False

Elastomers are Thermoplastic = changes in temperature affect which characteristics of
the polymer are predominant at any given time, and those changes are reversible. (T/F)
- CORRECT ANSWER-True

85-90% of the overall volume of HMA is occupied by aggregate. (T/F) - CORRECT
ANSWER-True

Nominal Maximum Size definition - CORRECT ANSWER-Sieve above the first sieve to
cumulatively retain more than 10% of material.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Brainarium Delaware State University
View profile
Follow You need to be logged in order to follow users or courses
Sold
1839
Member since
2 year
Number of followers
1043
Documents
22422
Last sold
2 hours ago

3.8

320 reviews

5
148
4
61
3
54
2
16
1
41

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions