True or False. Special provisions are contract documents that may describe Some
situation unique to a particular project or modify a Requirement set forth in the
Specifications. - Answer-True
True or False. Progress payments are made to contractors on the basis of monthly
progress estimates. - Answer-True
Which of the following are NOT types of final estimates documentation?
A. Truck Tabulation Forms and Computer Input
B. Final plans
C. Computation Book Forms
D. Unit Pricing and Estimates Procedure Manual
E. None of the above - Answer-D. Unit Pricing and Esimates Procedure Manual
What identification is missing from the front cover and the spine of the field notebook
shown below
A. Front Cover: Notebook number, Financial
1. Project ID NO., and the description of the contents
2. Spine: Fed Aid Aid No.
B. Font Cover: Notebook Number, Financial
1. Project ID No. and the description of Contents
2. Spine: Contract No.
C. Front Cover: Notebook Number, Financial
1. Project ID No. and description of contents
2. Spine: Notebook Number
D. Front Cover: Notebook Number, Financial
1. Project ID No. and the description of contents
2. Spine: Financial Project ID No.
E. None of the above - Answer-C. Front Cover: Notebook Number, Financial
1. Project ID No. and description of contents
2. Spine: Notebook Number
If any one field book entry is in error, how should the correction be made?
A. Correction cannot be made
B. Strike through and enter the correct data
, C. Strike through enter correct data, initial, and date
D. Circle incorrect data and initial, but do not enter correct data
E. None of the above - Answer-C. Strike through, enter correct data, initial, and date
A detailed page of Notebook contents should begin on the first lined page( page 1) of a
field book. True or false? - Answer-True
If an entire page of a field book is full of errors, what should you do to remedy the
situation?
A. Carefully remove the page and start on a new page.
B. Write the correct data on a new page.
C. Write the correct data on. A new page and mark the incorrect page void
D. Write the correct data on a new page, mark the incorrect page void and note where
the correct information is shown. Initial and date both pages.
E. None of the above. - Answer-D. Write the correct data on a new page, mark the
incorrect page void and note where the correct information is shown. Initial and date
both pages
You should keep notes on scratch pads and copy them in Notebooks at a later date so
that your entries will be neater. - Answer-False
7) Even though three financial project ID's are included in the same contract, you should
combine information from all three jobs in the same notebook. True or False - Answer-
False
1) "Check Levels" must be run at the start of a construction project to assure that:
A. Liquid Bituminous Material in Asphalt distributors is measured accurately.
B. Construction will be done to Contractor's elevation.
C. Final measurements for payment will be from the same base elevations as the
original survey and the construction will be done to design elevations.
D. Paver screeds are calibrated to lay down pavement of uniform thickness.
E. None of the above. - Answer-C. Final measurements for payment will be from the
same base elevations as the original survey and the construction will be done to design
elevations.
3) Multiple choice. Select the correct sequence of documents in order of precedence,
with the document highest in authority listed first.
A. Contract Plans, Development Specifications, Standard Specifications, Special
Provisions, Technical Special Provisions, Supplemental Specifications, Design
Standards.
B. Design Standards, Special Provisions, Technical Special Provisions, Supplemental
Specifications, Contract Plans, development Specifications, Standard Specifications.
C. Special Provisions, Technical Special Provisions, Contract Plans, Design Standards,
Development Specifications, Supplemental Specifications, Standard Specifications.
D. Supplemental Specifications, Special Provisions, Contract Plans, Development
Specifications, Standards Specifications, Technical Special Provisions, Design
QUESTIONS WITH COMPLETE
ANSWERS
True or False. Special provisions are contract documents that may describe Some
situation unique to a particular project or modify a Requirement set forth in the
Specifications. - Answer-True
True or False. Progress payments are made to contractors on the basis of monthly
progress estimates. - Answer-True
Which of the following are NOT types of final estimates documentation?
A. Truck Tabulation Forms and Computer Input
B. Final plans
C. Computation Book Forms
D. Unit Pricing and Estimates Procedure Manual
E. None of the above - Answer-D. Unit Pricing and Esimates Procedure Manual
What identification is missing from the front cover and the spine of the field notebook
shown below
A. Front Cover: Notebook number, Financial
1. Project ID NO., and the description of the contents
2. Spine: Fed Aid Aid No.
B. Font Cover: Notebook Number, Financial
1. Project ID No. and the description of Contents
2. Spine: Contract No.
C. Front Cover: Notebook Number, Financial
1. Project ID No. and description of contents
2. Spine: Notebook Number
D. Front Cover: Notebook Number, Financial
1. Project ID No. and the description of contents
2. Spine: Financial Project ID No.
E. None of the above - Answer-C. Front Cover: Notebook Number, Financial
1. Project ID No. and description of contents
2. Spine: Notebook Number
If any one field book entry is in error, how should the correction be made?
A. Correction cannot be made
B. Strike through and enter the correct data
, C. Strike through enter correct data, initial, and date
D. Circle incorrect data and initial, but do not enter correct data
E. None of the above - Answer-C. Strike through, enter correct data, initial, and date
A detailed page of Notebook contents should begin on the first lined page( page 1) of a
field book. True or false? - Answer-True
If an entire page of a field book is full of errors, what should you do to remedy the
situation?
A. Carefully remove the page and start on a new page.
B. Write the correct data on a new page.
C. Write the correct data on. A new page and mark the incorrect page void
D. Write the correct data on a new page, mark the incorrect page void and note where
the correct information is shown. Initial and date both pages.
E. None of the above. - Answer-D. Write the correct data on a new page, mark the
incorrect page void and note where the correct information is shown. Initial and date
both pages
You should keep notes on scratch pads and copy them in Notebooks at a later date so
that your entries will be neater. - Answer-False
7) Even though three financial project ID's are included in the same contract, you should
combine information from all three jobs in the same notebook. True or False - Answer-
False
1) "Check Levels" must be run at the start of a construction project to assure that:
A. Liquid Bituminous Material in Asphalt distributors is measured accurately.
B. Construction will be done to Contractor's elevation.
C. Final measurements for payment will be from the same base elevations as the
original survey and the construction will be done to design elevations.
D. Paver screeds are calibrated to lay down pavement of uniform thickness.
E. None of the above. - Answer-C. Final measurements for payment will be from the
same base elevations as the original survey and the construction will be done to design
elevations.
3) Multiple choice. Select the correct sequence of documents in order of precedence,
with the document highest in authority listed first.
A. Contract Plans, Development Specifications, Standard Specifications, Special
Provisions, Technical Special Provisions, Supplemental Specifications, Design
Standards.
B. Design Standards, Special Provisions, Technical Special Provisions, Supplemental
Specifications, Contract Plans, development Specifications, Standard Specifications.
C. Special Provisions, Technical Special Provisions, Contract Plans, Design Standards,
Development Specifications, Supplemental Specifications, Standard Specifications.
D. Supplemental Specifications, Special Provisions, Contract Plans, Development