A supply manager issues a request to proposal for engineering services. In order to provide clarification on the specification on the specifications, the company holds a question-and-answer session for interested suppliers. Shortly after the question-and-answer session is held and before any proposals are actually received, the firm's engineering department revises the specifications. Given this situation, which of the following should the supply manager do FIRST? (A) Call and email the suppliers of the change, tell them when the new specifications will be available, and ask for immediate notification if additional time will be required. (B) Write a letter to each supplier advising of the change, tell each supplier when the new specifications will be available, and ask for immediate notification if additional time will be required. (C) Hold an interim pre-bid meeting withal suppliers to discuss and clarify the revi -Correct Answer (A) Call and email the suppliers of the change, tell them when the new specifications will be available, and ask for immediate notification if additional time will be required. Which of the following should have the MOST influence in determining end product specifications, so as to minimize the potential for returns? (A) Marketing (B) Supply management (C) Engineering (D) Manufacturing -Correct Answer (A) Marketing When developing specifications, a buyer may consider information from which of the following? I. Suppliers II. Industry Standards III. Professional Organizations IV. Competitors (A) I and IV only (B) II and III only (C) I, II and III only (D) I, II, III and IV -Correct Answer (D) I, II, III and IV A supply manager completes a category profile and identifies services provided through multiple suppliers. A market and industry analysis shows that the service provides are growing their businesses by acquiring competitors, thus enabling them to provide a greater range of services. Which of the following techniques will BEST enable the supply manager to leverage market competition? (A) Lotting strategy (B) Market-basket model (C) Market segmentation (D) Sole sourcing -Correct Answer (A) Lotting strategy A supply manager implements a system whereby the potential supplier names are hidden until final contract awards are made. This example is BEST described as ensuring (A) confidential information is protected (B) diversity initiatives are met (C) total costs are minimized (D) collusion will not occur -Correct Answer (A) confidential information is protected A supply manager for a privately held manufacturing company is preparing an RFP for raw materials. None of the RFP recipients is an incumbent, and the award resulting from the RFP is expected to be of significant dollar value. The supply manager is concerned that the lack of publicly available financial information could impact willingness of the prospective suppliers to submit proposals. Which of the following will BEST address the concerns of the prospective bidders?

Show more Read less
Institution
CPSM Diagnostic
Course
CPSM Diagnostic











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CPSM Diagnostic
Course
CPSM Diagnostic

Document information

Uploaded on
July 4, 2025
Number of pages
49
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • cpsm diagnostic
  • cpsm

Content preview

CPSM



CPSM Diagnostic Practice Exam 1 Study
Guide Questions and Answers 2025
A supply manager issues a request to proposal for engineering services. In order to
provide clarification on the specification on the specifications, the company holds
a question-and-answer session for interested suppliers. Shortly after the question-
and-answer session is held and before any proposals are actually received, the
firm's engineering department revises the specifications. Given this situation,
which of the following should the supply manager do FIRST?

(A) Call and email the suppliers of the change, tell them when the new
specifications will be available, and ask for immediate notification if additional
time will be required.
(B) Write a letter to each supplier advising of the change, tell each supplier when
the new specifications will be available, and ask for immediate notification if
additional time will be required.
(C) Hold an interim pre-bid meeting withal suppliers to discuss and clarify the revi
-Correct Answer ✔(A) Call and email the suppliers of the change, tell them when
the new specifications will be available, and ask for immediate notification if
additional time will be required.

Which of the following should have the MOST influence in determining end
product specifications, so as to minimize the potential for returns?

(A) Marketing
(B) Supply management
(C) Engineering
(D) Manufacturing -Correct Answer ✔(A) Marketing

When developing specifications, a buyer may consider information from which of
the following?

I. Suppliers


CPSM

,CPSM


II. Industry Standards
III. Professional Organizations
IV. Competitors
(A) I and IV only
(B) II and III only
(C) I, II and III only
(D) I, II, III and IV -Correct Answer ✔(D) I, II, III and IV

A supply manager completes a category profile and identifies services provided
through multiple suppliers. A market and industry analysis shows that the service
provides are growing their businesses by acquiring competitors, thus enabling them
to provide a greater range of services. Which of the following techniques will
BEST enable the supply manager to leverage market competition?

(A) Lotting strategy
(B) Market-basket model
(C) Market segmentation
(D) Sole sourcing -Correct Answer ✔(A) Lotting strategy

A supply manager implements a system whereby the potential supplier names are
hidden until final contract awards are made. This example is BEST described as
ensuring

(A) confidential information is protected
(B) diversity initiatives are met
(C) total costs are minimized
(D) collusion will not occur -Correct Answer ✔(A) confidential information is
protected

A supply manager for a privately held manufacturing company is preparing an
RFP for raw materials. None of
the RFP recipients is an incumbent, and the award resulting from the RFP is
expected to be of significant dollar value. The supply manager is concerned that
the lack of publicly available financial information could impact willingness of the


CPSM

,CPSM


prospective suppliers to submit proposals. Which of the following will BEST
address the concerns of the prospective bidders?

(A) Escrow account
(B) Letter of credit
(C) Payment bond
(D) Surety bond -Correct Answer ✔(B) Letter of credit

Which of the following is the LEAST critical element in a best alternative to a
negotiated agreement (BATNA)?

(A) Alternate products
(B) In-house capabilities
(C) Source options
(D) Supplier capabilities -Correct Answer ✔(D) Supplier capabilities

A supply manager is negotiating with a critical supplier. The parties have relatively
equal bargaining power. Which of the following would MOST likely occur in
"win-win" negotiation between these parties?

(A) The supply manager and supplier conclude the negotiation by splitting the
difference between their respective positions.
(B) The supply manager and supplier each find concessions with equal
weight/value to provide a balanced outcome.
(C) The supply manager and supplier decide to share confidential information.
(D) The supply manager and supplier establish an appropriate settlement range for
the continuation of
negotiations. -Correct Answer ✔(B) The supply manager and supplier each find
concessions with equal weight/value to provide a balanced outcome.

An in-depth analysis of a supplier's proposal is useful because it is important to
understand the

(A) SOW throughout the evaluation process


CPSM

, CPSM


(B) SOW throughout the proposal development process
(C) supplier's proposal throughout the negotiation process
(D) supplier's firm-fixed price -Correct Answer ✔(C) supplier's proposal
throughout the negotiation process

Which of the following is LEAST appropriate as an objective for negotiations?

(A) Meeting the minimum essential needs of the organization
(B) Maintaining control over contract performance
(C) Determining the negotiation site
(D) Ensuring the correct ratio of contract administrators to workers -Correct
Answer ✔(D) Ensuring the correct ratio of contract administrators to workers

Which of the following is likely to be the BEST use of social media sites such as
LinkedIn during the preparation for negotiations with a potential supplier?

(A) Selecting the ideal negotiation sire
(B) Determining objectives for the negotiation
(C) Collecting information, reports and comments on the supplier
(D) Defining the roles and responsibilities of the negotiating team -Correct Answer
✔(C) Collecting information, reports and comments on the supplier.

A supply manager for XYZ Corp. is planning for negotiations with Supplier A, a
provider of software critical for use on XYZ's production line. XYZ likes the
software, but was recently alerted by Supplier A that they are dropping support for
the version that XYZ uses. The supply manager learns that an upgrade is cost
prohibitive for XYZ. Prior to negotiations, the supply manager asks the IT
department to detail its requirements for support of the software, and to assign an
IT employee to attend the negotiations. The day before the negotiation, the IT
employee calls the supply manager and stares that he
is unable to attend due to a scheduling conflict. He further states that he is
confident the supply manager can represent the IT department's needs in the
negotiations.
Given this scenario, which of the following should the supply manager do?


CPSM

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PossibleA Chamberlain College Of Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
982
Member since
4 year
Number of followers
650
Documents
12621
Last sold
2 days ago
POSSIBLEA QUALITY UPDATED EXAMS

Choose quality study materials for nursing schools to ensure success in your studies and future career. "Welcome to PossibleA - your perfect study assistant! Here you will find Quality sheets, study materials, exams, quizzes, tests, and notes to prepare for exams and study successfully. Our store offers a wide selection of materials on various subjects and difficulty levels, created by experienced teachers and checked for quality. Our quality sheets are an easy and quick way to remember key points and definitions. And our study materials, tests, and quizzes will help you absorb the material and prepare for exams. Our store also has notes and lecture summaries that will help you save time and make the learning process more efficient.

Read more Read less
3.9

140 reviews

5
74
4
24
3
20
2
1
1
21

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions